Eletronuclear has already presented a plan to accelerate work on the so-called critical line of the Angra 3 nuclear plant, where one of the priorities is to complete the so-called plant containment building
Good news, involving construction work on the Angra 3 nuclear power plant. To ensure that the plant goes into operation within the established schedule – in November 2026, Eletronuclear launches a public notice to hire compliance services, aiming at the implementation and execution of a program of corporate integrity for works on the plant's critical line. Eletronuclear receives an advance of 2,5 billion reais to resume work on the Angra 3 nuclear power plant in 2020
Read also
- Tender for the Itapu FPSO is cancelled; Petrobras closes deal with Shell and Petrogal for the purchase of FPSO P-71 for US$353 million
- Contractor that provided services for works by Petrobras, at Comperj, files for bankruptcy and 200 workers are at a loss
- 150 vacancies at Mercedes Benz! The German multinational manufacturer of luxury cars and trucks calls for professionals with no experience
The bid opened by the state-owned company is for specialized Compliance Services to support the Integrity area of ELETROBRAS ELETRONUCLEAR, encompassing risk assessment and auditing, aiming at the implementation and execution of a Specific Corporate Integrity Program (Compliance), dedicated to the services of the Critical Line of the development of Angra 3.
The announcement was published yesterday (27/10) and the delivery of proposals has already started. According to the publication, the opening of bids is scheduled for 14 pm on November 19.
- With a TRILLION DOLLAR investment in the railway sector, Brazil is on its way to becoming one of the greatest global powers, connecting to China and Peru!
- The government's fiscal adjustment causes an uproar in the Judiciary and could trigger mass retirement, generating chaos and compromising the replacement of magistrates in Brazil!
- Brazil invests R$468 billion to lead green revolution and ensure energy security until 2033
- Brazil leads growth in global aviation, but the rise in the dollar threatens companies, makes tickets more expensive and puts the sector's expansion at risk
It is worth mentioning that the state-owned company has already presented a plan to accelerate work on the so-called Angra 3 critical line, where one of the priorities is to complete the so-called plant containment building – the most complex building and with the greatest volume of work in the project by 2023. The start of operation of the Angra 3 nuclear plant is scheduled for 2026.
ELECTRONIC AUCTION No. DAN.A / PE-224/2020
- Eletrobrás Termonuclear S/A – ELETRONUCLEAR makes public that it will carry out a Bid in the Electronic Auction modality, lower price, for the Provision of specialized Compliance Services to support the Integrity area of ELETROBRAS ELETRONUCLEAR, encompassing risk assessment and auditing, aiming at the implementation and execution of a Specific Corporate Integrity Program (Compliance), dedicated to the services of the Critical Line of the Angra 3 project.
- The Public Notice can be withdrawn free of charge through the website www.comprasgovernamentais.gov.br, as of 27/10/2020.
- Submission of Proposals: from 27/10/2020 on the website www.comprasgovernamentais.gov.br.
- Opening of Proposals: at 14:00 (fourteen hours) on 19/11/2020, www.comprasgovernamental.gov.br
Publication Date: 27/10/2020