1. Início
  2. / Refinery and Thermal Power Plant
  3. / Marlim Azul Power Plant Works, Built in Macaé (RJ) and Financed by BNDES, Delayed by 206 Days
Localização RJ Tempo de leitura 2 min de leitura

Marlim Azul Power Plant Works, Built in Macaé (RJ) and Financed by BNDES, Delayed by 206 Days

Escrito por Roberta Souza
Publicado em 11/02/2023 às 10:35
Atualizado em 18/03/2023 às 17:09
usina - macaé - rj
Foto: Reprodução adaptada Ana Chaffin – Prefeitura de Macaé (RJ)
Seja o primeiro a reagir!
Reagir ao artigo

The Delivery Forecast of the Plant in Macaé Was for the Day 01/01/2023, but That Is Not What Happened. Understand:

According to the contract signed between the Marlim Azul thermoelectric plant and the pre-salt plant, a new plant financed by BNDES (valued at R$ 2.5 billion) in Macaé (RJ) was supposed to start generating energy on the 1st of this year. However, the plans were thwarted, as the plant was not delivered on time, according to Estadão.

The planning to complete the project for the plant was carried out with the creation of a consortium of Mitsubishi Hitachi with Pátria Investimentos and Shell, with construction starting in July 2020. In addition to the partners, the plant in Macaé, Rio de Janeiro, was financed by BNDES.

The Macaé plant has a generation capacity of 565 megawatts with just one turbine, enough to supply power to just over 2 million households. Furthermore, this plant was the only one to date that won a bid to explore gas from the Brazilian pre-salt.

Delays in the Plant Works

Delays in the construction of the new plant began during the Covid-19 pandemic, which, according to Marlim Azul Energia, pushed the schedule for the implementation of the plant back by 206 days. According to the balance conducted, all lockdowns, city closures and so on hindered the launch of the new plant.

Thus, the significant delay in the startup of the new plant in Macaé (RJ) rescheduled its activities to begin only on July 25. Sources from Estadão say that in May 2022, the company requested ANEEL for an extension for the delivery of the plant in RJ. The argument used by the company was that the pandemic delayed the delivery of the plant excessively.

Analyzing the company’s justification, ANEEL concluded that the argument presented does not match reality, since, in their view, the delay is related to internal issues within the company itself, involving contracts and changes.

Justification from Marlim Azul Energia

In light of ANEEL’s denial, the company presented other arguments justifying the delay in the delivery of the Macaé plant, thus requesting a review of the process. The material is under review and results have not yet been disclosed.

The solution for Marlim was then to acquire a plant for energy generation, thus attempting to honor commitments to energy distributors. Currently, the plant is 96% completed and has 900 employees active.

Roberta Souza

Autora no portal Click Petróleo e Gás desde 2019, responsável pela publicação de mais de 8.000 matérias que somam milhões de acessos, unindo técnica, clareza e engajamento para informar e conectar leitores. Engenheira de Petróleo e pós-graduada em Comissionamento de Unidades Industriais, também trago experiência prática e vivência no setor do agronegócio, o que amplia minha visão e versatilidade na produção de conteúdo especializado. Desenvolvo pautas, divulgo oportunidades de emprego e crio materiais publicitários direcionados para o público do setor. Para sugestões de pauta, divulgação de vagas ou propostas de publicidade, entre em contato pelo e-mail: santizatagpc@gmail.com. Não recebemos currículos

Compartilhar em aplicativos