1. Home
  2. / Construction
  3. / Italian giant of 130 tons arrives at the Senna Tower construction site and accelerates foundations: Mite CFA 3436 drills up to 50 m, 750 hp engine, investment of R$ 20 million, unique in Latin America.
Reading time 5 min of reading Comments 0 comments

Italian giant of 130 tons arrives at the Senna Tower construction site and accelerates foundations: Mite CFA 3436 drills up to 50 m, 750 hp engine, investment of R$ 20 million, unique in Latin America.

Written by Carla Teles
Published on 04/04/2026 at 09:49
Seja o primeiro a reagir!
Reagir ao artigo

At Senna Tower, the Mite CFA 3436 executes piles with in-hole concreting and rebar insertion to accelerate the foundations of the site

The Senna Tower site has received a significant boost for the foundation phase: a new Italian pile machine, presented on-site as the Mite CFA 3436. The operation takes place within the construction site, with concreting done directly in the hole and rebar inserted shortly after, in a process closely monitored by the team.

According to reports from the Senna Tower site, the foundation is already over 50% completed and the schedule is ahead of time. The arrival of the equipment serves as support to maintain pace, increase drilling capacity, and enhance productivity in this stage that defines the base of the project.

What is the Mite CFA 3436 and why does it stand out at Senna Tower

Senna Tower receives Mite CFA 3436 for piles with concreting and rebar and explains deep drilling and the pace of the foundations.

The machine presented at the Senna Tower site is described as a CFA drill with an unusual size, weighing over 120 tons and nearing 130 tons when equipped with the auger.

It is a large, wide, and stable structure, with a track widening system to further increase the base during operation.

Another highlight is the telescopic tower, which extends to gain height and increase drilling capacity. This also facilitates assembly and transportation on the Senna Tower site, as the tower can be retracted when necessary.

Drilling up to 50 m and 60 cm piles at Senna Tower

Senna Tower receives Mite CFA 3436 for piles with concreting and rebar and explains deep drilling and the pace of the foundations.

In the operation shown, the drilling indicated for the Mite CFA 3436 reaches up to 50 meters deep. In the monitored hole, the diameter used is 60 cm, and the process follows a practical sequence: drilling, removal of the auger, concreting through the hose, and then insertion of the rebar.

The very terrain of the Senna Tower is described with varying depths, with rock references in ranges approximately from 38 to 42, reaching up to 45 m, depending on the point. This causes the piles to vary and requires constant technical reading during drilling.

750 hp engine, seven pumps, and computerized operation

Senna Tower receives Mite CFA 3436 for piles with concreting and rebar and explains deep drilling and the pace of the foundations.

The Mite CFA 3436 presented at Senna Tower is described as a 100% computerized machine, with an operator’s cabin and monitoring of parameters during execution.

The engine is noted to have about 750 horsepower, positioned at the rear of the equipment, with two air filters visible in the structure.

During the explanation at the Senna Tower site, it is mentioned that the machine operates with seven pumps, and the operator discusses the dynamics of pressure and operation as the material changes.

A minimum torque of 300 bar is also mentioned, with readings varying according to soil conditions and the transition to rock.

When it reaches the rock: vibration, torque, and advancing centimeter by centimeter

Senna Tower receives Mite CFA 3436 for piles with concreting and rebar and explains deep drilling and the pace of the foundations.

One of the most striking moments of monitoring at Senna Tower is the transition from softer ground to rocky fragments and then to solid rock.

The operator describes that the machine starts to vibrate more, the speed decreases, and the advancement needs to be done carefully, at a much slower pace.

There is also a practical explanation of reading behavior: when the rock is smooth, the torque may decrease, and when there is relief, the torque tends to increase because the auger “nibbles” the irregularities. In the rocky section, drilling literally becomes a work of patience and control.

Concreting, “bubo,” and the pile profile at Senna Tower

YouTube video

After reaching the planned depth, concreting begins. The concrete is discharged and injected into the hole, with pressure readings in the system.

One point mentioned is the “bubo,” which in practice means allowing the concrete to settle and form a base at the bottom of the pile before pulling the auger.

In the monitored hole at Senna Tower, the panel shows the pile profile during concreting, and the final volume mentioned reaches 19.50 m³ of concrete in that cycle. This is the stage where the pile ceases to be just drilling and becomes a structure in fact.

Rebar insertion: crane, controlled zone, and spliced pieces

Senna Tower receives Mite CFA 3436 for piles with concreting and rebar and explains deep drilling and the pace of the foundations.

With the pile concreted, the insertion of rebar begins, done with the support of a crane, as the assembly is described as being over 30 meters long.

The rebar appears formed by spliced bars with clips, with variations in configuration depending on the pile.

At Senna Tower, it is also mentioned that the piles are fully reinforced and that the ground must undergo a lowering of about 9 to 10 m of excavation.

Therefore, the upper part of the pile is later leveled off, and the effectively utilized section is around 30 to 32 m.

Investment of around R$ 20 million and why it is unique in Latin America

The arrival of the Mite CFA 3436 at Senna Tower is associated with an investment described as around R$ 20 million to bring the equipment to Brazil.

The report states that it is the only machine of its kind in Latin America, with similar ones mentioned as being present in the United States and Europe.

The company responsible for bringing the equipment to the Senna Tower site is União Fundações, noted as being from the Santa Catarina region, with reference to Itapema.

What changes in the pace of the Senna Tower construction

In practice, the logic is productivity. A machine of this size allows for fast drilling in more favorable terrain, better control of the transition to rock, and keeps the pile cycle moving with concreting and rebar in sequence. For a project like Senna Tower, foundation means schedule. And schedule means cost.

By showing repositioning, stability pads, and the continuous operation of piles, the sensation conveyed is of a production line: while one pile receives rebar, the machine already starts drilling the next, keeping the Senna Tower site in motion.

Do you think a project like Senna Tower benefits more from giant machines like this or from more teams working in parallel with smaller equipment?

Inscreva-se
Notificar de
guest
0 Comentários
Mais recente
Mais antigos Mais votado
Feedbacks
Visualizar todos comentários
Carla Teles

Produzo conteúdos diários sobre economia, curiosidades, setor automotivo, tecnologia, inovação, construção e setor de petróleo e gás, com foco no que realmente importa para o mercado brasileiro. Aqui, você encontra oportunidades de trabalho atualizadas e as principais movimentações da indústria. Tem uma sugestão de pauta ou quer divulgar sua vaga? Fale comigo: carlatdl016@gmail.com

Share in apps
0
Adoraríamos sua opnião sobre esse assunto, comente!x