The Cabaçal mine, a gold, copper, and silver project by Meridian Mining in southwestern Mato Grosso, has entered the pre-construction phase with contracted engineering, orders for heavy equipment, and over 20 financing proposals on the table, but the final investment decision has not yet been made.
The announcement was made by the miner, listed in London and Toronto, in a market update on November 9. The statement details what has been contracted and what still depends on third-party funding.
For those living in the region, the number that carries the most weight is in the middle of the document: at the peak of construction, the project is expected to require over 1,300 people, and the mine’s operation afterward will need more than 600.
Over 20 Offers from Banks, Funds, and Trading Entities
According to Meridian, the company has completed an initial round of discussions with banks, funds, commodity trading companies, export credit agencies, and other financiers. The outcome was over 20 indicative proposals.
-
International Purchases Surge 67% After Blouse Tax Ends, ABVTEX Warns of New Factories in Paraguay Following Lupo’s R$ 30 Million Investment and Potential 30% Cost Reduction
-
Brazil Faces Engineering Workforce Shortage with Over 500,000 Engineers Needed and Only Six per 1,000 Inhabitants
-
JBS Requests Removal from Brazilian Public Company Registry, Transfers Issuer Structure to JBS N.V. in the Netherlands
-
Randon Ends Production in Chapecó After Over 10 Years, Moves Operations to SP and RS, Impacting Approximately 150 Workers with Closure of SC Unit
Several of these offer more than $300 million in debt. Some go further, assembling complete packages of $400 million, which include the project’s debt, a reserve for cost overruns, potential capital contributions, and sales services for the concentrate.
The crucial word here is indicative. No proposal is a credit commitment, and the company itself states that it is still analyzing the offers to create a shortlist of candidates and only then negotiate the details.
Cash on Hand Cannot Cover the Project Alone
The definitive feasibility study for Cabaçal estimates the pre-production investment at $322 million. As of September 30, Meridian had $90.1 million in cash, according to the third-quarter balance sheet released on November 13.
Therefore, financing is the missing piece. “To build Cabaçal, we need to structure project financing, and this has been in planning since 2024,” stated CEO Gilbert Clark in the release.
He noted he was not surprised by the strength of the proposals and attributed the interest to the economics of the project and the quality of the copper concentrate containing gold and silver that the mine is expected to produce.

The Numbers Attracting Financiers
The technical report of the study, dated October 28, indicates a net present value of $2.1 billion after taxes and an internal rate of return of 108%, with capital returned in 0.9 years.
These calculations use gold at $3,570 per ounce, copper at $5.03 per pound, and silver at $50.17 per ounce. If metal prices fall, returns diminish, and banks are particularly attentive to this before signing.
Proven and probable reserves total 56.04 million tons of ore, with 0.61 grams of gold per ton, 0.35% copper, and 1.33 grams of silver. Meridian projects an annual average of 183,526 gold equivalent ounces in the first five years.
In September, when the study was released, the portal already indicated how much gold and copper the Cabaçal project expects to extract over 14 years of operation. The new development now is the financing pathway.
AFRY to Handle Engineering from Belo Horizonte
To lead engineering, procurement, and construction management under the EPCM contract, Meridian has chosen AFRY, an engineering firm that has operated in Brazil since 1969 and employs around 1,450 professionals in the country.
According to the mining company, the capability to manage construction projects influenced their choice. AFRY has previously provided services to Aura Minerals, Nexa Resources in Mato Grosso, Hochschild Mining, and Ero Copper, among others.
The Meridian team responsible for the project will work from AFRY’s office in Belo Horizonte. The company states that the priority is to maximize Brazilian content in the construction of the mine.
US$ 30.9 million already committed before final decision
Even without a final investment decision, the mining company has already signed contracts totaling US$ 30.9 million for pre-construction activities. The list includes the engineering contract itself and transformers for energy supply.
Civil works outside the mining area are also included, such as bridges and road improvements, as well as three pieces of plant equipment: a SAG mill, Jameson flotation cells, and an IsaMill, which are all items with long lead times for delivery.
To oversee these activities, the company’s dedicated project team has increased to 13 professionals. According to the announcement, more management, engineering, and technical staff will be recruited at the appropriate time.

138 kV line to originate in Araputanga
The power for the mine will come via a 138 kV and 24.3 km transmission line that extends from the Araputanga substation, which connects to the national grid, to the plant area.
The declaration of public utility, authorizing the installation of structures along the route, has already been obtained, as has the installation license. The company is now conducting a bidding process to choose a contractor for the line construction.
The package includes reinforcing the connection substation, raising the line, and installing the substation that will supply power within the plant. Additionally, Meridian has already contracted engineering services to adapt the road access for heavy traffic.
Technical school in São José dos Quatro Marcos
The aspect that most interests job seekers in the region is the training plan. In partnership with the Federation of Industries of Mato Grosso, Fiemt, and through Senai, a technical school is being established in São José dos Quatro Marcos.
According to the mining company, this unit will train future mine employees. The company regards hiring people from nearby communities as a central aspect of the preparation for construction and operation.
However, the announcement does not provide the number of course places, opening date for registrations, or hiring schedule. Those who wish to prepare must still wait for future announcements from the company and Senai.

1,300 in construction, 600 in operation
The job count comes from Meridian itself: more than 1,300 people at the peak of construction and over 600 during the mine’s operation. These are projections, not open positions.
It’s the kind of project that typically involves electromechanical assembly, earthworks, civil construction, and industrial maintenance. It’s understandable that people are getting excited, but progress only happens when funding is secured.
What Still Needs to Happen Before the Project Starts
Meridian has not disclosed which institutions submitted proposals, which will be selected, the final structure between debt and equity, or the dates for the shortlist or final investment decision.
In the meantime, the company continues to explore Santa Helena and the Jauru and Araputanga belts, where it aims to increase the ore available for the complex.
From this perspective, Cabaçal seems closer to becoming a reality than it was in September, but the construction site with over a thousand workers still relies on the signature of a bank or a fund.