Antaq approved a study Thursday, November 12, 2026, by a 3-2 vote, to extend Eldorado Brasil’s terminal lease at Santos Port through 2091. The company also received until July 2027 to complete work at Berth 34
Eldorado Brasil Celulose has until July 2027 to finish work at its terminal at Santos Port, in São Paulo state. The company is controlled by J&F, owned by brothers Joesley and Wesley Batista.
InvestNews disclosed the new deadline Tuesday, November 17, 2026, in a report by Rikardy Tooge. The report also outlined the plan to extend the lease through 2091.
The decision by Brazil’s National Waterway Transportation Agency (Antaq) was issued Thursday, the 12th, and published the following day. The amendment changing the deadline for the work was signed in October.
-
MRV Launches R$ 138.4 Million Condominium with 372 Apartments in Olympic Barra, Concurrently Managing Construction and Sales in Rio’s Southwest Zone
-
Sabesp Builds Two Giant Metal Reservoirs Holding 30 Million Liters in Praia Grande, Invests R$175 Million, Closes Streets in Six Cities Until November 21, and Promises to Reinforce Supply for 238,000 People on the São Paulo Coast
-
Motiva Digs 21 Meters Below Taboão da Serra, Opens 3 Giant Wells Simultaneously, and Prepares Up to 10 Fronts to Bore 3.3 km of Tunnels for the Yellow Line for the First Time Outside São Paulo’s Capital
-
Rail minister Lord Hendy visited HS2’s Old Oak Common station after crews dug out 100,000 tonnes of London clay with excavators to finish two 360-metre tunnels and an 8.8-mile link to West Ruislip
Eldorado’s pulp terminal opened in July 2023. Both changes affect the same lease contract, which currently runs through 2046.
What work does Eldorado need to complete?
The work is concentrated at Berth 34, a section of quay added to Eldorado’s leased area in 2025. A berth is the space where ships dock to load and unload cargo.
The company will replace the mooring points and berthing protection. It also needs to improve the quay surface.
These improvements are Eldorado’s responsibility. They do not entitle the company to compensation under the lease.
Why was the deadline moved to July 2027?
Under the April 2025 agreement, Eldorado had 12 months to carry out the work at Berth 34. The original deadline was April 2026.
An amendment signed in October 2026 postponed completion. Under the amendment, the final deadline for the work moved to July 2027.
What did Antaq approve?
Antaq approved, by a 3-2 vote, a study proposing to extend the terminal lease from 2046 to 2091.
The proposal by rapporteur Caio Farias prevailed. The agency’s director general, Frederico Dias, and director Alexandre Florambel voted against it.
Extending the lease is the option under study to compensate for expenses recognized in the lease review. Antaq kept the proceedings confidential.
What expenses does Eldorado want compensated?
In 2025, Antaq had already recognized the company’s right to compensation for work outside the original contract. The items include an overpass, access roads and a pedestrian bridge.
Eldorado says the overpass and road system cost R$139 million. The pedestrian bridge cost R$5 million.
These are road and pedestrian access projects that were not included in the terminal’s original contract.
Even if operations continue through 2091, Antaq’s calculations indicate that part of the balance would remain uncompensated. The company itself would absorb that amount.
Is the additional 45 years guaranteed?
No. The extension depends on Brazil’s Ministry of Ports and Airports, which will determine how the compensation is structured.
The ministry will decide how Eldorado is compensated for the expenses on the overpass, access roads and pedestrian bridge.
With the ministry’s approval, Eldorado could operate in the Santos Port area for another 45 years, through 2091. The terminal lease currently runs through 2046.

What is Eldorado’s terminal in Santos like?
The terminal, known as EBLog, opened in July 2023 after an investment of R$550 million. It has the capacity to handle 3 million metric tons a year.
The opening ceremony took place on Monday, July 31, 2023, with then-Minister of Ports and Airports Márcio França in attendance.
At the time, Agência Gov reported an investment of R$500 million. The terminal could load pulp onto two ships at the same time, potentially tripling export volumes.
The facility has two berths, allowing simultaneous operations. Its 53,000-square-meter rail yard is equipped to receive trains, according to Eldorado.
Construction began in January 2022 and involved more than 500 people. The figure comes from Semadesc, a department of the Mato Grosso do Sul state government.
The terminal is used exclusively by Eldorado to ship pulp produced in Mato Grosso do Sul. Before it opened, the company used several shipping points at the Port of Santos.
For the terminal’s first anniversary, the BE News portal reported that it could accommodate up to 72 railcars and had 150 employees.
How much cargo has the terminal shipped?
By its third year of operations, on July 30, 2026, EBLog had shipped more than 2.35 million metric tons of pulp. It had handled 174 ships.
The 2.35-million-ton milestone was also reported by Agência iNFRA on August 4, 2026.
The daily record was set in April 2026, when 29,640 metric tons were shipped in a single day. Eldorado says average productivity rose 58.5% compared with its previous operation at the Port of Santos.
How did Eldorado secure this port site?
Eldorado won the site at an auction held by Antaq, Brazil’s waterway regulator, on August 28, 2020, paying R$250 million to the federal government, according to Tecnologística. The contract was signed on Monday, November 16, 2020.
Eldorado’s lease runs for 25 years. The site now has a pulp warehouse along the quay, with a dedicated berth and a connection to the rail network, according to Tecnologística.
Before EBLog, Eldorado operated in Santos at the former Rishis Terminal, according to Datamar News.
What does the port have to do with the Três Lagoas mill?
Eldorado produces 1.8 million tonnes of pulp a year in Três Lagoas, in the state of Mato Grosso do Sul. The company exports to more than 40 countries and has more than 5,000 employees.
The company is trying to move forward with a second production line in the city, which has been planned for more than a decade. It is part of a R$25 billion package announced in 2024 that includes a mill, forests and a railway.
The new line would add 2.6 million tonnes a year and bring Eldorado’s total capacity to 4.4 million tonnes. As of October, the expansion had no public timeline.
What decisions are still pending?
Two dates will shape Eldorado’s future at the Port of Santos. The first is July 2027, the deadline for completing work on Berth 34.
The second is 2091, which still depends on approval from Brazil’s Ministry of Ports and Airports. In the meantime, the terminal lease is set to expire in 2046.