A lightning strike hit Petrobras’ P-77 offshore platform on Wednesday, November 25, 2026, in the Búzios field, causing a small fire that was quickly contained. No one was injured. Sindipetro-RJ asked the company for an explanation
A lightning strike hit Petrobras’ P-77 offshore platform in the Búzios field and sparked a small fire that the onboard teams contained. The incident happened on Wednesday, November 25, 2026.
Agência Brasil published Petrobras’ statement on Thursday, November 26. Sindipetro-RJ released an internal account of the incident and a formal request for clarification on Friday, November 27.
For offshore workers, the incident shows how emergency response works on one of the largest platforms in Brazil’s pre-salt region.
-
Petrobras studies carbon capture hubs in four states, including Espírito Santo, and outlines plan to sell the service to other industries
-
ANP to require oil companies to report local-content plans for platforms over the next five years, citing risk of R$3.2 billion in commitments going unmet
-
Petrobras, Shell, and Galp could unlock R$24.5 billion from 2010 dispute with Brazil’s oil regulator and explain how Tupi could continue production after 2037
-
ANP approves studies for Gato do Mato’s Southeast block in Brazil’s pre-salt, estimates 193 million barrels and outlines path to auction
What Petrobras reported
Petrobras said the lightning strike hit P-77 and caused a small fire that was quickly extinguished. No one was injured, and no equipment was damaged.
“The company reiterates that the safety of people, facilities and the environment is a priority across all its operations,” Petrobras said in the statement published by Agência Brasil.
The internal incident report
Sindipetro-RJ reproduced an internal report published by the news site Tempo Real. The document describes a “small fire in the Port Aft Vent caused by lightning, triggering an ESD on the unit.” ESD is the platform’s emergency shutdown.
According to the report, the alarm sounded and the crew assembled at the muster point, where they were accounted for. The fire was fought using the platform’s fixed system and both CO2 banks.
Two firefighting boats were deployed: Marlim Flamengo, 4 miles away, about 30 minutes out, and Elisabeth C, 10 miles away. The emergency was under control at 6:09 a.m. on November 25, the report says.
Workers on a nearby unit told the union that weather had been severe since late in the night, with heavy rain, lightning and rough seas.
The scale of P-77
P-77 is an FPSO, a floating production, storage and offloading vessel that produces, stores and transfers oil. It is anchored about 200 kilometers (124 miles) off the coast of Rio de Janeiro, Agência Brasil reports.
The unit can produce up to 150,000 barrels of oil per day and compress up to 6 million cubic meters of natural gas per day. Both figures appear in reports by Agência Brasil and Sindipetro-RJ.
The platform operates in 1,980 meters of water in the Búzios field, in the pre-salt area of the Santos Basin.
In operation since 2019
P-77 has been operating since March 2019. Sindipetro-RJ notes that it was the fourth unit to begin production in Búzios.
The platform also features in sales of oil owned by Brazil’s federal government. At PPSA’s 11th Spot Auction on November 25, 2026, ExxonMobil won a cargo of about 500,000 barrels from P-77, according to MegaWhat.
What the union is demanding
Sindipetro-RJ says Petrobras limited its response to a press statement and provided no further information about the incident.
The union sent Letter 440/2026, formally requesting clarification and complete information about the fire on P-77. The platform is within Sindipetro-RJ’s jurisdiction.
Both sides of the story
Petrobras says the small fire was quickly extinguished and that there were no injuries or damage to equipment. The internal report cited by the union also states that there were no injuries or environmental damage.
The union wants more details about what happened on board. As of publication, Petrobras had not released its response to the formal request.
What offshore workers need to know
The P-77 incident shows the response sequence planned for a platform: an alarm, the crew gathering at the muster point, firefighting with the fixed system, and support from firefighting boats.