Brazilian shipyards are gaining momentum with contracts for ships, barges, and offshore support vessels. The industry had already passed 70,000 workers in May 2026, while financing, insurance, and professional training emerge as challenges to sustaining growth.
Brazilian shipbuilding has entered a new order cycle and could exceed 80,000 workers by the end of 2026, projections from the National Union of the Shipbuilding and Offshore Repair Industry (Sinaval) and the Brazilian Association of Companies in the Marine Economy (Abeemar) show. However, shipyards’ recovery faces challenges in hiring workers, securing financing for large projects and obtaining bank guarantees, a report published by Sinaval on August 31, 2026, said.
The recovery is supported by Transpetro shipbuilding contracts, inland waterway vessels, and ships supporting oil and gas operations.
The growing order book is also increasing demand for specialized suppliers of steel, equipment, engineering, and industrial services.
-
Collision Between Ships in India Entangles Anchor Chains, Causing Bulk Carrier with Nearly 86,000 Tons of Coal to Take On Water
-
Support Vessel Pulls Up to 105 Tons, Recovers 21 Structures at 770 Meters, and Completes Offshore Decommissioning 19 Days Ahead of Schedule in Brazil
-
1909 Crane to Have Its Upper Section Lowered by Floating Crane to Expose Hidden Wear and Guide Its Preservation at Nagasaki Shipyard
-
After Losing Thousands of Jobs During the Shipbuilding Crisis, Niterói Deepens Canal to Accommodate Larger Vessels, Invests R$ 162.5 Million in Infrastructure, and Seeks New Contracts with Petrobras and Transpetro as Shipyards Resume Production and Mauá Expands Workforce
Shipbuilding employment rose from about 23,000 jobs in 2023 to more than 70,000 workers in May 2026
The recovery in employment is one of the main indicators of the rebound in Brazilian shipbuilding.
Abeemar President João Azeredo said the industry had about 23,000 direct jobs in 2023, when companies and industry representatives resumed talks with Petrobras, Transpetro, and the federal government.
By May 2026, the number of workers had already topped 70,000.
The industry therefore recorded a sharp increase in its workforce in just over three years.
A projection released in August pointed to the possibility of exceeding 80,000 workers by December 2026. That would bring the industry closer to levels seen before the crisis that began in the previous decade.
The estimate, however, still depended on hiring trends and project progress.
Beyond direct jobs, Abeemar estimated more than 250,000 indirect jobs linked to shipbuilding.
Growth spans shipyards in Brazil’s North, Northeast, Southeast, and South, with particular activity in hubs specializing in support vessels and transport ships.
In Rio Grande do Sul state, for example, Ecovix projected that the Rio Grande Shipyard would reach 5,000 workers during the busiest period of its contracted projects.
The plan calls for building 13 ships under the Mar Aberto program over about five years.
Despite the hiring outlook, the company recognizes that some roles require specialized training.
Shipbuilding demands technical skills that differ from those required to manufacture modules for offshore platforms.
Transpetro plans to expand its fleet from 26 to 42 ships by 2030 with support from the Merchant Marine Fund
The Mar Aberto program is central to the new investment cycle.
Information presented by Transpetro in Sinaval’s report showed that the Merchant Marine Fund (FMM) Board had approved about R$ 5.2 billion for the company’s projects.
The funding covers four Handy-class ships, five gas carriers, four Medium Range 1 ships, and 36 vessels for inland waterway shipping.
The last group includes 18 barges and 18 tugboats.
With the planned contracts, Transpetro aims to expand its owned fleet from 26 to 42 ships by 2030.
In addition, the company’s president, Sérgio Bacci, said the funding needed for the contracts already signed was included in Petrobras’ investment portfolio.
By August 2026, the company had disbursed approximately R$ 100 million in initial payments for activities including steel purchases, insurance contracts, and preparations for construction.
The schedule presented called for the Handy ships to begin operations in May 2028.
Deliveries of the gas carriers and MR1 ships were to be staggered, depending on the effectiveness of the respective contracts.
For inland waterway shipping, the forecast called for the tugboats to enter service starting in October 2027.
However, approval of funding by the Merchant Marine Fund does not mean the financing will be released in full immediately. Financing depends on contracts, guarantees, and project milestones.
Shortage of bank guarantees and insurance coverage worth up to R$ 1.6 billion makes it harder for shipyards to secure new contracts
Although the Merchant Marine Fund has money available to finance projects, access to credit remains a challenge for some shipyards.
Abeemar says the difficulties worsened after Brazil’s shipbuilding crisis, which strained the cash flow of several companies.
Financial institutions now require bank guarantees that can significantly increase project costs.
In addition, shipbuilding contracts must meet insurance requirements that cover risks during construction.
One example arose during the contract to build the four Handymax ships.
More than 20 insurance and reinsurance companies were approached to make the project viable. Even so, some institutions declined to participate in the transaction.
The solution involved splitting the risks among four companies, which put together a policy worth approximately R$ 1.6 billion.
The episode shows that the availability of orders does not eliminate the financial difficulties faced by shipbuilders.
Industry representatives are therefore calling for credit and guarantee mechanisms better suited to the characteristics of the shipbuilding industry.
Rio de Janeiro shipyards resume hiring as industry seeks skilled workers and new technologies
The recovery is also bringing activity back to shipyards in the state of Rio de Janeiro that faced financial difficulties in recent years.
Estaleiro Mauá, in Niterói, ended the first half of 2026 with approximately 1,700 workers.
Between December 2024 and May 2026, the company created 621 jobs and reopened a welding school to train workers.
The shipyard has also expanded its work manufacturing steel structures for offshore projects.
The company is also building two PSV 4,500-type offshore support vessels, named Iara and Arlete.
Meanwhile, industry representatives are advocating greater use of automation, artificial intelligence, and robotic welding systems.
These solutions could boost productivity and ease some of the pressure caused by a shortage of skilled workers.
However, adopting new technologies requires investment, training, and a steady flow of orders.
The sector is also monitoring the regulations for the Tax Regime to Incentivize Shipbuilding Activity, known as Renaval.
For Sinaval, the competitiveness of Brazilian shipyards depends on tax conditions, access to credit, and predictable contracts.
The expansion of the ship order book creates opportunities for workers and suppliers, but sustaining that growth will depend on the ability to turn orders into financed and completed projects.