Customs clearance is part of preparations for the US$9 billion project, developed in partnership with Petrobras and Repsol Sinopec Brasil, which is expected to begin production in 2028.
Brazil’s Federal Revenue Service has cleared Equinor to use simplified customs procedures to export crude oil directly from the Raia FPSO, an offshore production vessel that is part of one of the largest oil and gas investments currently under development in Brazil.
The measure is set out in Executive Declaratory Act ALF/RJO No. 61, dated November 11, 2026, which grants the Norwegian oil company provisional authorization to clear exports directly from an offshore production unit.
The decision is part of the administrative preparations for the Raia project’s start-up in the Campos Basin, with investment estimated at US$9 billion.
-
British company unveils model promising to cut offshore facility decommissioning costs by 45% and North Sea operations timelines by 30%
-
Petrobras installs 4,425 seismic stations at a depth of 2,100 meters to monitor 220 km² of the pre-salt and boost oil recovery at Mero
-
Australian oil company plans to invest up to US$950 million to recover 60 million barrels of oil in the Santos Basin, reusing an FPSO and drilling four subsea wells, with production set to begin in 2030
-
Vår Energi strikes $4.4 billion deal to take over ConocoPhillips’ historic North Sea fields, targeting production above 500,000 barrels a day
Equinor will be able to export oil directly from an offshore platform
The authorization is based on Normative Instruction RFB No. 1,381, dated July 31, 2013, which governs simplified customs procedures for Brazilian crude oil exports.
Under this model, oil produced and stored on the platform can be transferred to ships that transport the commodity, with export procedures carried out directly offshore.
Preparing customs procedures before production begins is particularly important for projects of this scale, where the oil evacuation logistics must be aligned with the platform’s operating capacity.
The project remains under development, with operations scheduled to begin in 2028.
US$9 billion megaproject brings together Equinor, Petrobras and Repsol Sinopec
Located in the Campos Basin pre-salt offshore Brazil, the Raia project has more than 1 billion barrels of oil equivalent in recoverable natural gas, oil and condensate reserves.
Three companies are developing the project:
- Equinor: 35% stake and operator.
- Repsol Sinopec Brasil: 35%.
- Petrobras: 30%.
According to Equinor, the FPSO will have capacity to process about 126,000 barrels of oil per day and handle 16 million cubic meters of natural gas per day. Equinor+2
The drilling campaign, which began in March 2026, includes six subsea wells connected to the future platform.
200-kilometer gas pipeline will connect the Raia FPSO to shore
The project also includes dedicated infrastructure to transport natural gas from the platform to Cabiúnas, in the municipality of Macaé, in Rio de Janeiro state.
Equinor has completed installation of 186 kilometers of the ultra-deepwater section, using pipes made with 99% Brazilian steel.
One of the project’s main innovations is processing natural gas on the platform itself, allowing it to connect to Brazil’s gas transportation network without an additional onshore processing step.
The Raia project’s official information says its supply capacity could account for about 15% of Brazil’s projected natural gas demand in 2028. Equinor+1
As the project advances through engineering, drilling and construction, the customs clearance authorization granted by Brazil’s Federal Revenue Service sets some of the customs requirements needed for the future export of oil.