Iberdrola showed a video on Monday, October 26, 2026, of the repowering work at the Muras wind farm in Lugo, Galicia. The 74 turbines rated at 660 kW each, installed in 1998, are being replaced by 11 machines rated at 4.3 MW, and the wind farm continues to supply 40,000 homes
Iberdrola is replacing an entire wind farm in Galicia, in northern Spain. A forest of 74 old turbines is making way for just 11 giant machines.
The company showed the progress of the work in a video published on YouTube on Monday, October 26, 2026. The project was authorized by the Xunta de Galicia, the region’s government.
-
Panasonic transforms glass windows into solar power plants, accelerates mass production of perovskite technology and begins selling first units for buildings
-
Tesla integrates transformer, switch, and inverter into a single 7.4-MW unit, operable from -40°C to 55°C, offering warranties up to 25 years, with U.S.-made Powercore expected in 2027
-
BYD ties battery plant decision in Amazonas, investing up to R$500 million and producing 10 GW, to December 2 and 4 auctions, negotiating with 70 interested companies
-
ENGIE tests robot that efficiently cleans solar panels without water, boosts energy output by 5.4%, prepares further R$4.5 million investments
The technical details come from a December 14, 2023, announcement and documents from the Galician government, which authorized the project on March 4, 2025.
What Iberdrola showed in the video
The video is 37 seconds long and has already passed 550,000 views. Its description sums up the idea: an upgrade, or how “less” becomes “more.”
The footage shows cranes raising the new towers and enormous blades lying on the ground.
It also shows the Iberdrola-branded nacelle being lifted through the fog.
A crane unloads a transformer from a truck, while an overhead camera shows workers on a concrete foundation.
The message on screen is direct. The wind farm will go from 74 turbines to 11.
Each new turbine generates more than six times as much energy as its predecessor. Clean energy will continue to reach 40,000 homes.
Where the Muras wind farm is located
The wind farm is in the municipalities of Muras and Ourol, in the province of Lugo, Galicia. It has been operating since 1998 and has a capacity of 49 MW, according to Iberdrola’s 2023 announcement, published by the Spanish news site Bolsamanía.
At the time, the company said Muras supplied 41,000 homes a year. In the 2026 video, the figure shown is 40,000 homes.
The project is being run by Iberdrola Renovables Galicia, which is based in Ourense.
The official notice in Galicia’s official gazette, dated September 3, 2024, calls the project the “technological renewal of the 47.3-MW Muras wind farm.”
The machines being removed
The site currently has 74 G47 wind turbines, each rated at 0.66 MW, with rotor hubs 45 meters above the ground. Together, they have a capacity of 48.84 MW.
The Xunta, Galicia’s regional government, detailed what is being removed: the 74 turbines, 74 transformer stations, the underground medium-voltage network and two meteorological towers.
Roads that are no longer needed will be restored. The overhead medium-voltage line will also lose its 3.61-kilometer central circuit.

The machines being installed
They will be replaced by 11 Vestas V117 wind turbines, each rated at 4.3 MW. The rotor has a diameter of 117 meters, and its hub is 84 meters above the ground.
The 11 new machines have a combined capacity of 47.3 MW. In other words, there will be fewer turbines and nearly the same installed capacity, with far fewer towers spread across the mountain range.
Each turbine has a 5,150 kVA dry-type transformer at the base of its tower, which raises the voltage from 0.72 kV to 30 kV. 30 kV cables connect the machines to the substation.
What will change at the Muras substation
The Muras substation is also being upgraded. The old medium-voltage switchgear cells will be removed and replaced with new 30 kV cells.
The two old 132/20 kV, 30 MVA transformers will be removed. One 132/30 kV, 55 MVA transformer with an on-load tap changer will take their place.
Civil works include an access road, an internal road network, turbine foundations, assembly platforms, a storage area, cable trenches and drainage.
How much the project will cost
The construction budget published in Galicia’s Official Gazette is 39,390,366.79 euros.
The Xunta, Galicia’s regional government, put the cost at about 43 million euros when it authorized the project. That figure includes dismantling the old machines and installing the new ones.
The Xunta announced the authorization in a statement on Tuesday, March 4, 2025. The resolution was signed by the Directorate-General for Renewable Energy and Climate Change.
How much energy the new wind farm will generate
The repowered wind farm is expected to produce 155,886 MWh net per year, according to the Xunta.
Iberdrola says each new turbine generates more than six times as much energy as its predecessor.
In 2023, the company had already said the new machines would have up to six times the capacity of the first wind turbines installed in Spain.
The promised result is to keep supplying about 40,000 homes with far fewer turbines on the landscape.
Why Iberdrola is doing this
The process is called repowering.
The old wind turbines are dismantled and replaced with modern machines that make better use of the wind and produce more electricity, the website Energías Renovables explained in December 2023.

The turbines being removed were installed about a quarter-century ago.
The Xunta, Galicia’s regional government, says voluntary repowering can cut the number of turbines at a wind farm by up to 80% and increase renewable capacity by 35%.
In the year before that authorization, the Galician government reviewed nine projects of this kind.
The other wind farms on the list
Muras is part of a package of four wind farms that Iberdrola announced on December 14, 2023, in Galicia and Castilla-La Mancha.
At Serra da Panda, in A Coruña, the 18.5-MW wind farm, built in 2002, is being reduced from 24 turbines to five.
It currently has 22 turbines rated at 660 kW and two rated at 2 MW. After the upgrade, it will have three rated at 4.3 MW and the two 2-MW turbines. The wind farm supplies electricity to 12,600 households.
At Molar de Molinar, in Albacete, the 49.5-MW wind farm, built in 2001, is replacing 75 turbines rated at 660 kW with 11 rated at 4.5 MW. It supplies electricity to 29,500 homes, according to Forbes Spain.
At Isabela, also in Albacete, the 48-MW wind farm is going from 64 turbines rated at 750 kW to 11: six rated at 4.5 MW and five at 4.2 MW.
In Galicia alone, the number of turbines will fall by 82. Across the package, the total reduction is 200 turbines, while average output rises by 30%.
The package was included in the first round of the Repotenciación Circular grant program, run by Spain’s Ministry for the Ecological Transition through IDAE.
Iberdrola’s footprint in Spanish wind power
In 2023, when it announced the package, Iberdrola had nearly 200 wind installations across 13 of Spain’s autonomous communities, with 6,550 MW of capacity, according to Forbes Spain.
Worldwide, it had more than 41,000 MW of installed renewable capacity, including more than 20,000 MW of onshore wind power.
What remains to be done at Muras
A video from October 2026 shows the work progressing, with new towers standing and components being brought to the mountaintop.
Construction is still underway. Iberdrola ends the video by recalling its 125-year history in the energy sector.
Is replacing dozens of old turbines with a handful of giant machines the best path for wind power?