Construction Works for Spillway at Doutor da Vale Dam Will Provide Over 300 Jobs in Minas Gerais
The mining company Vale is expected to soon begin construction on a spillway channel, also known as a spillway, at a dam in Minas Gerais, with an anticipated completion in 2021. The works have already been reported to the State Secretary of Environment and Sustainable Development (Semad) and will require about 300 job vacancies, of which 200 have already been filled by local workers hired through Sine.
Read Also
- Studies Show That Renewable Sources, Such as Solar and Wind Energy, Are Cheaper Than Previously Thought
- Petrobras Receives Proposals for the Management of the Búzios 5 Project This Thursday
- Shell to Enter Brazil’s Offshore Wind Energy Market: “A Matter of Time”
In order to maintain the water level of the Vale dam’s reservoir lowered and to increase the safety and stability of the structure, the works are part of the first phase of the decharacterization process. They will be carried out at the Doutor Dam of the Timbopeba Mine, in the municipality of Ouro Preto, Minas Gerais.
-
Only 37 meters remain for Brazil and Paraguay to “close” the bioceanic bridge on the Bioceanic Route: the project worth R$ 575 million is at 89% completion, uses 14,000 tons of steel, and aims to finish the connection by the end of April.
-
The new era of civil construction features “dry construction” and boosts a company that accelerates expansion with 48 stores and steel frame.
-
Woman enters abandoned houses for 16 years that no one dared to visit: beautiful project and logical layout, interior mold-free, possible resort; after exploring, decides to buy everything for €32,000 and surprises the entire village.
-
Simple 2-bedroom house: a study of the construction sector reveals the real cost that few expect and shows how strategic decisions can prevent losses and ensure significant savings in the dream of homeownership.
Residents in the new Self-Rescue Zone (ZAS) are being relocated to other properties in the new planned removal phase, based on the validation by the audit of the Public Prosecutor’s Office of Minas Gerais of the last flooding spot of the Vale dam.
Execution Phases of Vale’s Works in Minas Gerais
The works on Vale’s spillway will be carried out gradually in peripheral areas of the dam, with the initial phase including vegetation suppression services, land cleaning, earthmoving, and channel excavation.
Immediately after the completion of the spillway, there will be the implementation of external reinforcements to the dam, environmental recovery, and reintegration of the area into the local environment, continuing the decharacterization of the Doutor Dam operated by the mining company Vale.
Monitoring
Vale will constantly monitor the indicators of water usage, air quality, and noise levels to ensure the effectiveness of control actions during the execution of the works, and ongoing actions to strengthen the dam’s safety in Minas Gerais are also being carried out.
Additionally, measures will be taken by the mining company Vale to prevent the spread of the new coronavirus among workers and residents in the Minas Gerais region, according to the recommendations of the World Health Organization (WHO) and other authorities.