Eletronuclear Is Responsible for Works at Angra 3 Nuclear Power Plant, MPF Requests Payment of R$30 Million and Requires IBAMA Not to Issue New Licenses for Project Progress
The MPF (Federal Public Prosecutor’s Office) wants the construction of the Angra 3 nuclear power plant to remain halted until Eletronuclear pays the environmental compensation agreed upon with IBAMA (Brazilian Institute of Environment and Renewable Natural Resources).
Read Also
- Not Again! Comperj May Have Works Delayed Once More Until 2019, Understand!
- Petrobras Reduc Refinery Has Its Activities Partially Halted and State Company is Summoned by MPF to Pay R$50 Million
- MPF Demands Over R$20 Billion from Braskem for Damage Caused by Rock Salt Extraction in Maceió
- Techint Construction Company is Accused by Operation Car Wash for Corruption Practices at Petrobras
Angra 3 Nuclear Power Plant May Have Bidding Annulled by MPF
When requesting authorization to build the power plant, Eletronuclear assumed a series of commitments such as actions directed at the local population and an investment of R$50 million in sanitation for Angra dos Reis and Paraty.
If the conditions are not met, the construction license may be annulled and the operating permit will not be issued.
-
Electrolux surprises, closes colossal factory and lays off 400 people in a mass dismissal that will have a direct effect later this year, following a cost review, with an impact of R$ 272.5 million and R$ 109 million in cash in Chile.
-
The Lula government is pursuing re-election and is therefore preparing a package with discounts of up to 80% on debts, subsidies for diesel, gas for 15 million, and energy, after reaching 51% disapproval six months before the election.
-
The chamber approves a project that transforms plots of up to 2,000 square meters into official rural properties, allowing thousands of small producers who were invisible to the government to now access credit, tax exemptions, and technical assistance.
-
Factory 52, in the USA, cost over $5 billion, covers 270,000 square meters, and manufactures cutting-edge chips: it was named Project of the Year by the world’s largest engineering magazine, marking the global race for semiconductors.
MPF Requests IBAMA Not to Issue Any Renewals, New License, or Environmental Installation Authorization for Eletronuclear to Start Operations at Angra 3
The MPF prosecutors also demanded that any and all eventual renewals involving the Angra 3 nuclear power plant be suspended in case of non-payment. The main objective of the MPF prosecutors is to prevent Eletronuclear from carrying out any activity involving the Angra 3 power plant.
Finally, the MPF also wishes for the company responsible for the Angra 3 nuclear power plant to present to IBAMA an updated sustainable plan and pay a fine of R$30 million. In a statement, Eletronuclear explained that it has not yet been officially notified of the action and therefore cannot comment at this time.
Angra 3 will be the third plant of the Almirante Álvaro Alberto Nuclear Power Center (CNAAA), located at Itaorna beach in Angra dos Reis (RJ). When it begins commercial operation, the new unit with a capacity of 1,405 megawatts will be able to generate over 12 million megawatt-hours per year, enough energy to supply the cities of Brasília and Belo Horizonte during the same period. With Angra 3, nuclear energy will account for 50% of the consumption of the State of Rio de Janeiro.