  3. Santos launches R$183.6 million waterfront overhaul after 20 years, rerouting 23 bus lines
Leave a comment 5 min of reading

Santos launches R$183.6 million waterfront overhaul after 20 years, rerouting 23 bus lines

Author profile image Carla Teles
Written by Carla Teles Published on 24/11/2026 at 23:28 Updated on 24/11/2026 at 23:29
Google News
Be the first to react!
React to this article
Prefer CPG on Google

Work began on Avenida Presidente Wilson, between Canal 1 and Rua Olavo Bilac, and includes new pavement, drainage and accessibility upgrades.

The Santos city government, in the coastal state of São Paulo, began work Monday (November 23, 2026) on a waterfront revitalization project, starting with the removal of old asphalt from Avenida Presidente Wilson between Canal 1 and Rua Olavo Bilac. The project is part of a R$183.6 million package to modernize five road corridors, after roughly 20 years in which the avenue along the beach received mainly spot improvements.

Information released by the Santos city government on November 23 said the start of work led to closures on the roadway heading toward Ponta da Praia and changes to the routes of 23 bus lines. The first phase is expected to end on December 18, before work along the waterfront is suspended for the year-end holidays and summer season.

Santos begins asphalt removal ahead of nearly 12-kilometer waterfront overhaul

Santos begins waterfront revitalization with asphalt work and a R3.6 million package. See the road closures, 23 affected bus lines and project deadlines.
Image: Santos city government.

Work began with pavement milling, a process in which machines remove the surface layer of deteriorated asphalt. This prepares the road for a new surface, correcting uneven areas and restoring driving conditions.

The first work zone is on Avenida Presidente Wilson, heading from José Menino toward Ponta da Praia. Crews began between Canal 1 and Rua Olavo Bilac, with work expected to continue as far as Rua Almirante Custódio de Mello.

The full project covers Avenida Presidente Wilson, Avenida Vicente de Carvalho and Avenida Bartolomeu de Gusmão. It will rehabilitate 11.9 kilometers of waterfront roadway, including 5.93 kilometers in each direction, from the boundary with São Vicente in José Menino to Rua Carlos de Campos in Ponta da Praia.

The work is the first structural overhaul of this corridor in about two decades, according to a CBN Santos report published November 24. During that period, the area received localized repairs, but no comprehensive upgrade of its road infrastructure.

Construction will be divided into 11 phases, with an estimated overall timeline of 18 months. The phased approach is intended to allow crews to upgrade different sections without shutting down traffic along the entire waterfront at once.

Work affects 23 bus lines and closes a section between Canals 1 and 2

The start of the work immediately changed drivers’ routines. The Santos Traffic Engineering Company (CET-Santos) closed the waterfront roadway between Channels 1 and 2 starting at 9 a.m. Monday, deploying traffic officers to direct drivers onto detours.

Vehicles heading toward Ponta da Praia should take Senador Pinheiro Machado Avenue at Channel 1, then turn onto Floriano Peixoto Avenue. Drivers can return to the beachfront avenue via Bernardino de Campos Avenue at Channel 2.

Francisco Glicério Avenue was also designated as an alternative route. Temporary parking restrictions were introduced on the streets used for detours to make more room for traffic.

The changes affect 17 intercity bus routes and six city routes, which now use Floriano Peixoto Avenue during the work. Routes 37, 959, 963 and 965 continue to Ana Costa Avenue before resuming their regular itineraries, while the others return to the waterfront via Channel 2.

CET-Santos data show that the beachfront corridor carries an average of nearly 2,000 vehicles per hour on weekdays. During the morning rush, from 6 a.m. to 9 a.m., about 185 buses travel through the area, underscoring the need for special arrangements for public transit.

The city government said it will monitor traffic around the clock and may make adjustments as work progresses. Drivers can also check for updated conditions on the Waze app.

R$183.6 million project includes drainage, accessible ramps and new bus stops

Santos begins waterfront revitalization with roadwork and a R3.6 million investment package. See the closures, 23 affected bus routes and timelines.
Image: Santos City Hall.

The revitalization involves more than replacing the asphalt. The project presented by the city government on November 19 includes improvements to drainage, accessibility, signage and urban infrastructure along the five avenues covered by the plan.

The package includes 4,669 meters of new drainage lines, repairs to 713 storm drains and construction of 175 more. New gutters are also planned to channel rainwater and reduce problems caused by water accumulating on the roadway.

Accessibility upgrades include 612 ramps, as well as the construction and repair of sidewalks designed for pedestrian traffic. The city also plans to build 63 bus bays, allowing vehicles to stop outside the main traffic flow.

Along the waterfront, bus stops at designated locations will receive rigid pavement. Concrete in these areas can better withstand the repeated stress caused by buses braking and accelerating.

The project also includes planting 551 trees, installing 488 trash bins and placing about 15,000 meters of traffic-signal cabling and 72,300 meters of telecommunications lines underground.

The traditional Portuguese-style mosaic sidewalks will be preserved, with spot repairs made as needed. The measure preserves a familiar feature of Santos’ urban landscape while the roadway and infrastructure facilities are modernized.

International financing covers R$ 146.8 million of the investment

The R$ 183.6 million contract was signed with Consórcio Santos Infraestrutura, which won the international tender to carry out the project.

Of that total, R$ 146.8 million comes from financing by the Development Bank of Latin America and the Caribbean (CAF). The remaining approximately R$ 36.8 million will be covered by municipal funds.

The work is part of the Santos Mais program, which brings together projects focused on urban infrastructure, mobility and the modernization of public services.

The waterfront revitalization is taking place as the city pursues other initiatives related to its coastal infrastructure. CPG has also covered Santos’ R$ 200 million plan, backed by BNDES, to prepare interventions addressing flooding and the effects of rising sea levels.

These are separate initiatives, each with its own funding sources and objectives. In the roadway revitalization, the announced investment is directly tied to restoring the avenues and improving traffic conditions.

In another Brazilian coastal city, the revitalization of Balneário Camboriú’s Central Beach also involves urban improvements, although its technical features differ from the pavement work in Santos.

Waterfront work will pause in December and resume after the summer season

Santos begins waterfront revitalization with asphalt work and a R$ 183.6 million package. See the road closures, the 23 bus routes affected and the timelines.
Image: Santos City Hall.

The first phase of Presidente Wilson Avenue is expected to be completed by December 18, 2026. The schedule released by Santos City Hall calls for work along the waterfront to be suspended from December 19 through January 31, 2027, to reduce its impact during the summer season.

The pause was built into the schedule and does not, by itself, constitute a contract delay. The city plans to resume work on the beachfront avenue after the busiest period for tourism.

Meanwhile, work on other sections of the project will begin in 2027. On Ana Costa Avenue, work is scheduled to start on January 4, between Rangel Pestana and Lucas Fortunato streets, heading toward the beach. Bernardino de Campos Avenue, known as Canal 2, will also undergo work early in the year.

In the first week, the city government expects to begin laying the new asphalt, weather permitting. Starting November 30, crews are expected to begin repairing curbs and gutters and building two concrete bus bays.

Pigmented concrete pedestrian crossings are scheduled to be installed on December 7. Road signs and markings will be installed later, after the previous stages are completed.

The overall schedule sets April 2028 as the expected completion date for work on the five road corridors, subject to changes due to operational or weather conditions. Until then, drivers and public transit riders should follow traffic changes announced by CET-Santos, the city’s traffic agency.

Sign up
Notify of
guest
0 Comments
most recent
older Most voted
Tags
Carla Teles

I produce daily content on economics, diverse topics, the automotive sector, technology, innovation, construction, and the oil and gas sector, with a focus on what truly matters to the Brazilian market. Here, you will find updated job opportunities and key industry developments. Have a content suggestion or want to advertise your job opening? Contact me: carlatdl016@gmail.com

0
I'd love to hear your opinion, please comment.x