  3. R$71.6 Million Bridge in Paraná Reaches 47% Completion, Paving the Way to End Ferry Crossing on the Ivaí River
Leave a comment 6 min of reading

R$71.6 Million Bridge in Paraná Reaches 47% Completion, Paving the Way to End Ferry Crossing on the Ivaí River

Author profile image Carla Teles
Written by Carla Teles Published on 24/11/2026 at 22:43 Updated on 24/11/2026 at 22:44
Google News
Be the first to react!
React to this article
Prefer CPG on Google

The 400-meter bridge will connect Japurá and São Carlos do Ivaí via PR-498; crews are working in the river and on the approach roads, with completion expected in 2028.

Construction of the new R$71.6 million bridge over the Ivaí River in northwestern Paraná has reached 47.12% completion, and work has advanced to pouring concrete for the piers in the river. The 400-meter structure will connect São Carlos do Ivaí and Japurá via PR-498 and replace the ferry crossing currently in use. Work completed to date totals R$33.7 million, and completion is expected in February 2028.

The Government of Paraná released the figures on November 23, 2026, based on monitoring by the Paraná Department of Highways (DER/PR). Although work is progressing on both riverbanks, frequent rain has hampered the earthworks needed to build the road approaches.

Work advances on 400-meter Ivaí River bridge as crews pour concrete for riverbed piers

Floating construction platform with a crane beside the concrete piers of the bridge over the Ivaí River.
Crews are using floating platforms and equipment to build the central piers of the new bridge. Image: DER/PR.

Construction is focused on the structures that will support the bridge deck, the surface on which vehicles will travel. In the central section, crews are working from barges and platforms to pour concrete for the six pairs of piers in the Ivaí River.

On the riverbanks, the five planned pairs of piers have already received their crossbeams, structural components installed on top of the supports. These elements help distribute the loads carried by the girders that will support the roadway.

The construction site is also producing the main girders and precast concrete slabs. The girders run lengthwise along the bridge, while the precast slabs will help form the deck.

The DER/PR says the components are being prefabricated on site for use in upcoming phases. Progress on this work does not mean the roadway is ready: the components that will allow vehicles to cross still need to be assembled and completed.

The project was 45.39% complete on October 23 and reached 47.12% in the November assessment. That is a gain of 1.73 percentage points in one month, a period marked by rain that also disrupted work outside the river.

New bridge will have two traffic lanes, shoulders and concrete side barriers

The revised design calls for a bridge 400 meters long and 13.40 meters wide, sized to carry traffic in both directions on PR-498.

It will have two 3.60-meter traffic lanes, with 2.50-meter shoulders on each side. The remaining width will be used for safety strips and side barriers.

These barriers will follow the New Jersey profile, made up of concrete structures used to contain or redirect vehicles in certain types of crashes. The configuration will also separate the traffic area from the edge of the structure.

A change was made during the project’s development. When the contract was announced in February 2025, the preliminary design called for a bridge 360 meters long.

In documents published in October and November 2026, DER/PR began reporting a length of 400 meters. The figure used in the latest progress updates is therefore different from the one presented when the contract was first awarded.

The project was designed to provide a permanent road connection between the municipalities. Completion will depend on both assembling the structure over the river and finishing the roadways that will connect the bridge to the existing highway.

Rainfall hampers paving of 1,180 meters of new access roads to PR-498

Aerial view of a ferry carrying a truck and car across the Ivaí River in Paraná, Brazil.
A ferry carries vehicles across the Ivaí River at the site of the planned permanent road connection. Image: Publicity.

In addition to the main crossing, the contract includes building 1,180 meters of road approaches along both banks of the Ivaí River.

These sections will connect the new bridge to the PR-498 route. Until the approach roads are complete, the structure will not be able to serve as a permanent link between the municipalities.

Rainfall in recent weeks has hampered earthworks in particular, according to the Paraná state Department of Infrastructure and Logistics. This stage involves moving and compacting soil to create the platform that will support the pavement layers.

The approaches will have 3.60-meter-wide lanes and 2.50-meter shoulders at the bridge ends. The pavement will use cement-stabilized materials in the lower layers and hot-mix asphalt concrete on the driving surface.

Drainage systems, pavement markings, road signs and traffic safety equipment are also planned. Drainage will channel rainwater and protect pavement structures from problems associated with moisture buildup.

This work is part of a broader wave of road improvements across the state. CPG has also covered the upgrade of PR-151 between Ponta Grossa and Palmeira, a project that also includes widening roadways and expanding crossing structures.

End of ferry service expected to change residents’ commutes and farm shipments

The connection between São Carlos do Ivaí and Japurá currently relies on a ferry service, which depends on operating conditions at the crossing and the state of the river.

Once the bridge is complete, vehicles will be able to cross the Ivaí River directly on the highway, without taking the ferry. The change will benefit residents who use the route for everyday travel, as well as freight transport between municipalities in the region.

The project also addresses a longstanding demand from the local population. In March 2026, the Paraná state government held a groundbreaking ceremony and presented the investment as a solution to replace the existing ferry service.

The new connection is expected to make road transportation easier and improve access to services in nearby municipalities. However, the government’s latest bulletin did not provide an official estimate of how many vehicles will benefit each day or how much travel time will be saved once the bridge opens.

Permanent bridges are also replacing ferries in other parts of Paraná. In May, CPG published an article about the bridge over the Corumbataí River, a project planned to improve regional connections and reduce reliance on river crossings.

On the Ivaí River, the February 2028 deadline means the ferry will remain necessary until the bridge and its access roads are complete and open to traffic.

R$71.6 million contract calls for bridge to be completed in February 2028

Watch the video

YouTube video

The Paraná Department of Highways (DER/PR) awarded the construction contract in February 2025, with an investment of R$ 71.592.000,00. The integrated contract covers both engineering design and construction.

Under this model, the contractor is responsible for several stages of the project, from preparing the designs to delivering the planned infrastructure. DER/PR oversees the work and reviews the proposed solutions against the contract requirements.

The R$ 33.737.821,38 reported in November represents the investment made up to that point, not the project’s total budget. Physical progress should also not automatically be taken as equivalent to the share of the budget spent.

The new crossing was officially named the Heitor Baggio Bridge under State Law No. 22.974, enacted in February 2026.

The current schedule calls for completion in February 2028, although factors such as weather conditions and construction of the remaining structures could affect the pace of work.

Upcoming work includes continuing to pour concrete for the piers in the river, installing the bridge deck girders, and advancing earthworks and paving on the access roads.

No opening date has been confirmed. Updates in upcoming DER/PR bulletins will make it possible to track progress on the main structure and road connections ahead of the planned delivery.

Sign up
Notify of
guest
0 Comments
most recent
older Most voted
Carla Teles

I produce daily content on economics, diverse topics, the automotive sector, technology, innovation, construction, and the oil and gas sector, with a focus on what truly matters to the Brazilian market. Here, you will find updated job opportunities and key industry developments. Have a content suggestion or want to advertise your job opening? Contact me: carlatdl016@gmail.com

0
I'd love to hear your opinion, please comment.x