A 30-year contract renewal calls for restoring rail infrastructure and returning decommissioned sections of the former Northeast Network. Studies identify trains’ low commercial speeds as a major obstacle to expanding freight transport in the region.
Brazil’s National Land Transportation Agency (ANTT) approved the opening of a public hearing on Monday (23) to discuss extending the concession held by Ferrovia Transnordestina Logística (FTL), a company in the Companhia Siderúrgica Nacional (CSN) group.
In a statement published Tuesday (24), the agency said it will accept comments on a draft contract addendum and the technical studies underpinning the investments and obligations proposed for the concessionaire from 2027 to 2057.
-
Nine cargo flights and more than 45 tractor-trailers move 800 metric tons of Formula 1 cars and equipment from Mexico to Interlagos before heading to Las Vegas
-
Nineteen railcars break free during grain transfer, travel nearly 8 kilometers uncontrolled, and hit two locomotives near Romania-Ukraine border
-
France’s new high-speed train gains a passenger car and 17% more space without increasing its 200-meter length; modular interiors allow class conversion in one day
-
Imported goods reach São Paulo in as little as seven days: Amazon cuts international delivery times by about 40% since 2024 and now offers 55 million products in Brazil
The current contract expires in December 2027 and covers rail segments across the states of Maranhão, Piauí, Ceará, Rio Grande do Norte, Paraíba, Pernambuco and Alagoas, although some of the infrastructure is out of service.
The reorganization of the concession would keep under FTL’s administration the rail corridor linking the Port of Itaqui in São Luís, Maranhão, to the Port of Mucuripe in Fortaleza, Ceará.
Investments in railcars, locomotives and rail infrastructure
Commitments proposed for the new contract period include R$521 million to acquire 1,000 railcars and R$205 million for 41 locomotives, Agência iNFRA reported in a report.
Together, the two purchases amount to R$726 million, or about 13% of the R$5.6 billion in investments proposed as part of the concession extension.
The plan also allocates R$43 million for work on bridges and overpasses, along with R$56.5 million for pedestrian overpasses, walls and signaling at grade crossings, where railway tracks intersect roads.
Infrastructure upgrades are expected to accompany the fleet renewal. The concession studies, detailed by Agência iNFRA, identify low commercial speeds as a constraint on freight growth, even though the railway has available capacity.
The studies project that track modernization will shorten travel times and allow more trains to run each day.
Freight transport across northeastern states
FTL’s operations focus on fuel shipments, particularly supplies to Piauí, but Brazil’s Ministry of Transport sees opportunities to diversify the goods carried by the concessionaire.
In an interview with Agência iNFRA, Transport Minister George Santoro linked the investments to the need to restore the railway’s operating capacity. “It’s about getting back to a position where we can carry freight,” he said.
Santoro cited serving companies in the mining sector and attracting customers that now use trucks to move their goods as potential opportunities.
Santoro also mentioned the possibility of connecting with the New Transnordestina, a railway operated by Transnordestina Logística S.A. (TLSA). Its concession covers a link between Eliseu Martins, in Piauí, and the Port of Pecém in Ceará.
Return of more than 3,000 kilometers of rail lines
The proposal submitted by Brazil’s National Land Transportation Agency (ANTT) includes the return of approximately 3,014 kilometers of non-operational rail lines as part of the reorganization of the concession.
The measure is part of an agreement between the federal government and the concessionaire that was approved by Brazil’s Federal Court of Accounts (TCU) in October this year, as reported by Agência iNFRA.
The agreement calls for the concessionaire to pay approximately R$1.8 billion in compensation, with the funds earmarked for investment in the remaining rail infrastructure.
For the returned segments, the proposal establishes obligations related to decommissioning the structures, regularizing land use, addressing environmental liabilities, and identifying the geographic boundaries of areas belonging to the railway.
ANTT public hearing to hold sessions in four cities
The period for submitting comments opens on December 2, 2026, and ends on January 15, 2027, at 11:59 p.m. Brasília time. Participants can submit comments online through the ParticipANTT system.
The schedule published in Public Hearing Notice No. 17/2026 sets out four sessions:
- December 7: São Luís (MA), at 2 p.m., in person.
- December 9: Brasília (DF), at 10 a.m., in a hybrid format.
- December 14: Teresina (PI), at 2 p.m., in person.
- December 16: Fortaleza (CE), at 10 a.m., in person.
The notice issued by ANTT differs from the official notice: it lists the Brasília session as in person and the Fortaleza session as hybrid. Both documents say all four sessions will be streamed on the agency’s YouTube channel.
Rail users, representatives of the business community and other interested parties may submit suggestions on investments, technical studies and the terms for operating the infrastructure. The hearing is not intended to reopen discussion of the agreement approved by the TCU.
Authorization to hold the public consultation does not constitute final approval of the contract renewal or award of the planned investments.
After the public comment period, the concession extension proposal is to be submitted to the TCU for review.