A 338-meter tunnel is linked beneath a São José dos Campos neighborhood using a trenchless method, but the drainage project still requires lining and finishing work

Author profile image Alisson Ficher
Written by Alisson Ficher Published on 20/11/2026 at 04:56 Updated on 20/11/2026 at 04:57
Google News
Be the first to react!
React to this article
Prefer CPG on Google

The underground passage connects a drainage conduit restored in 2019 to a pipe near Roberto Baranov Street. Built at depths ranging from seven to 15 meters, the structure was accessed through five vertical shafts during construction. The remaining work includes completing the drainage system and restoring the roadway.

A new stormwater drainage conduit in Jardim Imperial, in the southern part of São José dos Campos, Brazil, has been connected to the existing network. The structure was built to replace a section of the old pipe that collapsed during rainstorms early this year.

The connection was made on Felisbina de Souza Machado Street and announced Wednesday (the 18th), based on information from the city government reported by the Todo Dia Vale news site. Despite the progress, the project has not yet been completed, as additional work is needed before the pavement can be fully restored.

The tunnel was built using a trenchless method, which reduces the need for open excavations along the street and limits disruption at the surface. The project is the second phase of repairs to the neighborhood’s drainage system.

About 15 meters of concrete lining remain at the end of the tunnel, along with cleaning the work area and decommissioning the old, damaged conduit.

How the tunnel beneath Jardim Imperial was built

The new passage was built parallel to the structure that collapsed. This layout made it possible to construct the tunnel without first removing the entire compromised pipe before building the new drainage network.

The route connects two points in the existing system: the conduit rebuilt in 2019 near Antônio Moreira Vita Square, and the concrete pipe at the intersection of Felisbina de Souza Machado Street and Roberto Baranov Street.

To reach the underground work area, crews opened five vertical access shafts. These structures provide entry points for workers, equipment and materials needed for construction, without requiring a continuous trench along the entire route.

The trenchless method allows surface work to be concentrated around these access points, while the passage is built directly underground. At the Jardim Imperial site, the depth ranges from seven to 15 meters, depending on the section.

The structure uses metal components and has concrete lining along its lower section. The protection is intended to limit the metal’s exposure to corrosion, including the risk of sewage being improperly discharged into the network designed to carry rainwater.

The conduit was built to carry rainwater collected by the region’s drainage system. Building it parallel to the compromised section also made it possible to separate construction of the new passage from the work needed to decommission the old structure.

What work remains to restore the street

With the underground passage connected, Terrax, the company responsible for building the tunnel, is finishing additional work. This phase includes lining the remaining section, cleaning the work area and decommissioning the damaged pipe.

The city government said it expects to finish this work in the coming days, weather permitting. The announcement, however, did not set a final date for completion of all phases of the project.

After this phase, the Municipal Urban Development Company (Urbam) will be responsible for the third and final stage of the project, focused on restoring the surface of Felisbina de Souza Machado Street and completing the connections needed to put the drainage system into operation.

Planned work includes closing the vertical access shafts used during construction, installing precast storm drains and connecting the collection laterals to manholes.

Storm drains collect water flowing along streets during rain, while collection laterals carry it to the underground network. Manholes, in turn, provide access to the structure for inspections and maintenance work.

Restoration of the asphalt pavement and redevelopment of the area will take place after the drainage work, in keeping with the planned sequence of work for the project.

Failure of old conduit caused erosion and led to building closure

The need to replace part of the network arose after sections of the old conduit failed during heavy rains in late January and early February this year.

The failure caused the ground to sink at two locations on Felisbina de Souza Machado Street. The resulting instability also led to the preventive closure of a residential building because of risks associated with the erosion that had opened up nearby.

Urbam was responsible for the first phase of the project, stabilizing the ground and filling the erosion areas with layers of stone. These measures brought the emergency under control and made it possible for residents to return to the building.

Before the tunnel was built, the city government also conducted topographic surveys, a robotic inspection of the pipe and precautionary inspections of neighboring properties. The work provided information on the condition of existing infrastructure and nearby areas.

Construction of the new conduit began in April, after the emergency work was completed. Terrax took charge of the underground phase, installing the vertical access shafts and assembling the metal structure along the new route.

Agreement provides for R$9.4 million investment to restore the conduit

The drainage system restoration was also slated to receive state and municipal funding. In a statement released by the city government in June this year, the administration said the agreement for construction of the new structure totaled R$ 9.434.726,23.

Of that amount, R$ 7.547.780,98 is the planned contribution from the São Paulo state government, while R$ 1.886.945,25 is the municipal matching share.

The agreement stipulates that the funds be transferred to the city government, which is responsible for releasing payments to the company as work progresses. The disclosed amounts represent the investment planned under the agreement, not necessarily the total already disbursed for the project.

Sign up
Notify of
guest
0 Comments
most recent
older Most voted
Alisson Ficher

A journalist who graduated in 2017 and has been active in the field since 2015, with six years of experience in print magazines, stints at free-to-air TV channels, and over 12,000 online publications. A specialist in politics, employment, economics, courses, and other topics, he is also the editor of the CPG portal. Professional registration: 0087134/SP. If you have any questions, wish to report an error, or suggest a story idea related to the topics covered on the website, please contact via email: alisson.hficher@outlook.com. We do not accept résumés!

Share in apps
Download app
0
I'd love to hear your opinion, please comment.x