World Bank-funded megaproject in Vietnam calls for seven bridges, 60 kilometers of river dredging and a channel for 100-ton vessels, along with drainage works to combat flooding in Da Nang
Vietnam has begun moving a megaproject in Da Nang forward, combining seven bridges, 60 kilometers of river dredging and flood-control works. With an investment of about $113 million and funding from the World Bank, the initiative already has three bridges under construction, with further stages planned for 2027.
The project covers eight communes and wards in southeastern Da Nang, a region that incorporated the former province of Quảng Nam. The work combines road infrastructure, river transport and drainage systems.
Da Nang city’s official website lists the project budget at 2.723 trillion Vietnamese dong. Of that amount, 1.8385 trillion dong comes from World Bank financing.
-
Residents of Louisiana’s Vermilion Parish have until December 16 to weigh in on SpaceX’s plan for a 15.5-mile heavy-haul road, a 1.53-mile elevated bridge and a 3,500-foot wharf at its future spaceport
-
Engineers from France, South Korea and Vietnam will spend 30 months designing Vietnam’s 1,541-km high-speed railway, a US$67.34 billion line built for 350 km/h between Hanoi and Ho Chi Minh City
-
Vietnam advances $28.56 billion Hanoi megaproject spanning 11,400 hectares, bringing major construction groups together to reshape urban areas and expand infrastructure
-
Kenya builds new 880-meter-long bridge 100 meters above the Nithi River to replace dangerous crossing that has killed more than 60 people since 2018
The remaining 884.2 billion dong is the local counterpart, the share that the authorities responsible for carrying out the work must provide.
Seven bridges are part of Da Nang megaproject
The plan calls for six new bridges over the Trường Giang River and a community bridge to replace an existing structure.
Work on Bình Dương Bridge, in Thăng An commune, began in May 2026.
By the progress report released in November, crews had produced 11 of the 30 planned Super-T girders. These concrete components have a structural shape used to support the bridge deck.
Crews had also completed 19 of the 37 planned bored piles for one of the structure’s support areas.
Construction of Tỉnh Thủy Bridge began in June, and eight of its 56 piles had been completed.
Work on Bình Nam Bridge began in October. The contract for Hưng Mỹ Bridge was awarded in November.
Authorities scheduled construction of Tam Tiến Bridge and the community bridge to begin in December 2026. Tam Thanh remains in the planning and adjustment stage, with work scheduled for February 2027.
River to be dredged for 60 kilometers to accommodate 100-ton vessels
Another part of the project involves dredging the Trường Giang River, divided into two contracts covering kilometers 0 to 30 and 30 to 60.
The project calls for a navigable channel 30 meters wide and 2.3 meters deep, designed for vessels weighing up to 100 tons.
Companies to carry out the work are still being selected. Dredging is expected to begin in the first quarter of 2027.
2.38-kilometer canal is part of flood-control system
Along with the bridges and river transport, the project includes a drainage system in the Tam Kỳ area.
One of the planned interventions is the A3 channel, about 2.38 kilometers long, connecting Đầm River Lake to the Trường Giang River.
The structure is part of measures planned to improve water drainage and reduce flooding in the region.
Land acquisition affects 931 parcels and delays construction
Despite active construction, securing the land remains one of the main obstacles.
A 31-kilometer section in the communes of Thăng An and Thăng Trường affects 931 parcels. In another area, only 1.4 kilometers of an 8.5-kilometer channel had been cleared.
Authorities aim to complete land clearance before December 2027.
More than 253 billion Vietnamese dong had already been disbursed, equal to 88.8% of the funding budgeted for 2026, the Da Nang newspaper reported. en.baodanang.vn
The budget forecast for 2027 is 677 billion dong.
Trần Nam Hưng, vice chairman of the municipal government, ordered action to resolve outstanding issues with five contract packages that have not yet gone to tender and to prepare support measures for residents affected by the work.