Residents of Vermilion Parish, Louisiana, have until December 16 to comment on SpaceX’s request to build a 15.5-mile heavy-haul road, a 1.53-mile elevated bridge and a 3,500-foot wharf for its planned spaceport near Pecan Island.
The state put the coastal use permit application, number P20260831, out for public comment with a legal notice published on Saturday, November 21, in The Advocate, Acadiana News First reported.
It is the first big state permit for the project to reach the public. The Louisiana Department of Conservation and Energy lists it as the “Southwest Louisiana Coastal Infrastructure Improvement Project”, with Space Exploration Technologies Corp. as the applicant.
25 days for anyone to object or ask for a hearing
Comments will be received for 25 days from the date of the notice. The department’s calendar shows the period running from November 21 to December 16.
-
Engineers from France, South Korea and Vietnam will spend 30 months designing Vietnam’s 1,541-km high-speed railway, a US$67.34 billion line built for 350 km/h between Hanoi and Ho Chi Minh City
-
Vietnam advances $28.56 billion Hanoi megaproject spanning 11,400 hectares, bringing major construction groups together to reshape urban areas and expand infrastructure
-
Kenya builds new 880-meter-long bridge 100 meters above the Nithi River to replace dangerous crossing that has killed more than 60 people since 2018
-
Dubai Crown Prince Sheikh Hamdan says 14,000 workers have put 33 million hours into the Dh20.5 billion Metro Blue Line, now nearly 30% complete, as Dubai revealed new trains for up to 1,246 passengers.
The department is asking for written comments, including suggested changes or objections with the reasons for them. Anyone may request that a state or federal public hearing be held.
The review gives residents and other interested parties a chance to raise questions about effects on wetlands, waterways, navigation and nearby communities, according to the notice as described by Acadiana News First.

A road with four 12-foot lanes and a 1.53-mile bridge
According to the application, SpaceX plans to build a 15.5-mile heavy-haul access road on a 161-acre site. It would have four 12-foot travel lanes, 12-foot raised concrete medians and two 10-foot shoulders.
The road includes a 1.53-mile elevated bridge and would connect regional highways to the wharf components, Acadiana News First reported.
The Vermilion Times, citing an earlier version of the filing, described a road of about 15.75 miles with a 1.5-mile bridge and work running from 2027 to 2032.
A 3,500-foot wharf on the Freshwater Bayou Channel
The main structure is a moderate-draft wharf of 3,500 feet on the Freshwater Bayou Channel, south of the U.S. Army Corps of Engineers’ Freshwater City Lock.
Plans call for 133 acres for staging equipment south of the locks and another 90 acres north of them. The application also covers inland wharves along existing channels with barge access to the Freshwater Bayou and the Gulf Intracoastal Waterway.
More than 1 million cubic yards of dredged material
The area around the wharf will need to be dredged to a depth of 16 feet. That work is expected to produce more than 1 million cubic yards of dredge material, the application states.
Maintenance dredging for access is part of the request as well, along with a temporary laydown yard north of the locks.

Louisiana-made parts shipped to Texas and Florida
The revised application filed in November says the large wharf will let SpaceX ship Louisiana-made components and equipment to the company’s space operations in Florida, Texas and elsewhere.
In August, Elon Musk, SpaceX representatives and state and local officials announced plans for a $100 billion rocket launch and recovery site with five launch pads near Pecan Island. We covered that announcement when SpaceX bet $100 billion on a mega-base.
Sent back as incomplete on October 1
The state’s online permit tracker shows how the file moved, according to The Vermilion Times. On October 1, the state sent the application back to the engineering firm that filed it as incomplete.
On November 17 it was marked complete and sent to the Army Corps and the State Land Office. On November 18 it went to The Advocate for the legal notice and to the Department of Wildlife and Fisheries. On November 19 it moved to the Department of Environmental Quality.
No decision yet, and a separate federal review
The tracker lists the application as received and under review. It does not show a decision or a hearing date.
The federal side is separate: the Army Corps of Engineers reviews the same application under its own rules. Comments can be sent by mail, fax or email to the reviewer at the Office of Permitting and Compliance, quoting the permit number.
The public notice and electronic files are on the Louisiana Department of Conservation and Energy website.
If you lived or fished near Freshwater Bayou, would a 3,500-foot SpaceX wharf be a job engine or a threat to the marsh?