Reconstruction of BR-470 in Rio Grande do Sul is more than 90% complete, with over R$700 million invested in viaducts, slopes and bridge repairs.
Reconstruction of BR-470 between the Rio Grande do Sul municipalities of Bento Gonçalves and Veranópolis has entered its final stage after receiving more than R$700 million in investment from Brazil’s federal government. With more than 90% of the work completed, Brazil’s National Department of Transport Infrastructure (DNIT) is working to repair damage caused by the 2024 climate disaster and strengthen protection along the highway in areas of the Serra das Antas vulnerable to landslides.
In addition to repairing the roadway, the project includes engineering work designed to prevent further damage, including the construction of steel viaducts, repairs to an important bridge in the region and slope-stabilization measures.
Steel viaducts on BR-470 allow debris to pass beneath them during landslides
To reduce the risks posed by ground movement on two curved sections of the Serra das Antas, DNIT adopted a design that allows debris to pass beneath the viaducts. The metal structures are designed with wide clearances between their piers, reducing the chance that material from future landslides will hit the roadway directly.
-
Porto Alegre completes R$60 million flood-protection project with 8 pumps and 7 gates
-
Construction of Brazil’s R$174 million orthopedic hospital in Guará moves forward after delays
-
Rio Grande do Sul Prison Expands by 128 Beds with Completion of R$6.4 Million Project in Four Months
-
Santos launches R$183.6 million waterfront overhaul after 20 years, rerouting 23 bus lines
With approximately R$52.3 million in investment, the two viaducts differ in size and completion status:
- Viaduct at kilometer 193: It is 126 meters long and 17 meters high, with completion expected by the end of 2026;
- Viaduct at kilometer 192: It is already open to traffic and measures 85 meters long and 15 meters high.
The design of these structures also aims to reduce the need for frequent work on the terrain and minimize the risk of traffic disruptions on the highway.

Alongside the new construction, DNIT is working to restore one of the region’s best-known landmarks, the Ernesto Dornelles Bridge. The crossing over the Antas River received R$12.9 million in investment, and 96% of its rehabilitation work has been completed.
The work is part of the Structural Maintenance and Rehabilitation Program (PROARTE), which includes reinforcing and repairing the bridge’s hangers, girders and piers. The initiative aims to extend the structure’s service life and improve safety for the thousands of people who travel daily between the Serra Gaúcha region and the Rio das Antas Valley.
Highway protection work expands to 117 sites, with R$640 million in investment
Of the 117 projects planned to protect Brazil’s BR-470 highway from landslides, only 15 remain to be completed. Nine are at the initial stage, with their detailed engineering designs finalized, while six others are under way, including construction of the second viaduct.
The other 102 projects have been completed, matching the number of sites included in the DNIT’s initial plan.
The project’s scope expanded as work progressed, after inspections in the Serra das Antas revealed conditions requiring additional engineering work. These needs were incorporated into the detailed designs, broadening the road rehabilitation and protection effort.
Investment in this part of the project totals approximately R$640 million, funding work intended to improve slope stability and reduce the highway infrastructure’s exposure to future landslides.
Work in the Serra das Antas also includes installing drainage systems and repairing the pavement, complementing the protection measures implemented by the department along the highway.