PPT-53 began producing oil on November 26 after approval from Ibama. With both new wells at the Papa-Terra field in the Campos Basin online, Brava’s campaign is continuing in Atlanta, where first oil is expected in 2027.
Brava Energia brought well PPT-53 online on November 26, 2026, at the Papa-Terra field in the Campos Basin. Operations began after approval from the Brazilian Institute of Environment and Renewable Natural Resources (Ibama), Brazil’s environmental agency, as detailed in the material disclosure filed by the company.
With PPT-53 online, both wells planned for the Papa-Terra field as part of the integrated campaign are now producing. PPT-52 began operating on September 29. The campaign’s other two wells are in Atlanta, in the Santos Basin, and still need to be connected to the production system. Brava’s announcement on the start of PPT-52 production.
PPT-53 was already connected to the floating production vessel before approval
By November, drilling, completion and the tieback of PPT-53 to the 3R-3 floating production vessel had been completed. Completion involves installing the equipment needed to control well production. The tieback connects the well to the facility that receives and processes the extracted fluids.
-
Petrobras seeks a subsea robot weighing up to 30 kg to use heat against invasive sun coral colonizing oil platforms
-
After 7,000 hours of recordings in the Santos Basin, Brazilian Navy to produce underwater acoustic systems with OceanPact Tech
-
Foresea accumulates $1.7 billion in offshore drilling contracts, keeps five Petrobras-linked rigs operational until 2027, expands operations with PRIO
-
Brazil’s Federal Government receives 291,000 barrels of oil per day as output from pre-salt production-sharing contracts reaches 1.95 million barrels a day, with Mero leading the government’s oil take
With those steps complete, PPT-53 was awaiting regulatory approval to begin operating. Production started on November 26, but the well’s initial flow rate has not been disclosed. The Papa-Terra field is in the southern part of the Campos Basin, off Rio de Janeiro. Brava’s report on the campaign’s progress · Field development plan filed with Brazil’s National Agency of Petroleum, Natural Gas and Biofuels (ANP).
Lone Star rig is now working at Atlanta in the Santos Basin
Brava moved the Lone Star from the Papa-Terra field to Atlanta after completing drilling at the Campos Basin field. In Atlanta, the rig began work in November on the phase covering wells ATL-9H and ATL-10H. Brava’s announcement on drilling in Atlanta.

In the schedule released with its quarterly results, Brava said tieback work at Atlanta is set to begin in the first quarter of 2027, with first oil expected in the second quarter. These are the next milestones in the four-well campaign.