The Paraguay River bridge on BR-262 in Corumbá, in Brazil’s state of Mato Grosso do Sul, will be completely closed from 5 p.m. Wednesday (25) to noon Thursday (26). Traffic will be halted for 19 hours so crews can place concrete on another section of the rehabilitation project, which is now 75% complete.
The state government’s news agency posted the notice Saturday (21). This is the seventh of 11 full closures scheduled for the bridge’s structural rehabilitation. The bridge connects Corumbá and Ladário with the rest of the country.
Four more closures will follow. Dates for the next ones have not been announced, and Agesul, the state roads agency, communicates each closure in advance.
Times are based on Mato Grosso do Sul’s local clock
The closure begins at 5 p.m. Wednesday (25) and ends at noon Thursday (26), local time in Mato Grosso do Sul, one hour behind Brasília time.
-
Brazilian Iron Ore Freight Rate to China Increases by 17% in November
-
Uruguay launches $102 million freight rail service on a 265-km line, aiming to bring southern Brazil cargo to the port of Montevideo via a route to Rivera on the Rio Grande do Sul border
-
CMA CGM removes Manaus from service via Panama Canal, rerouting Asia cargo to Free Trade Zone through Rio de Janeiro transshipment in 11 days
-
Brazil’s Sorghum Shipments to China Reach 1.64 Million Metric Tons from August to October, Boosting Demand for Panamax Ships as Santos Handles 46% of Cargoes
Drivers coming from Campo Grande or São Paulo need to account for the time difference before setting out. In Brasília time, the bridge closes at 6 p.m. Wednesday and reopens at 1 p.m. Thursday.
The bridge was closed for the same length of time last week. From Wednesday (18) to Thursday (19), it was also shut for 19 hours, from 5 p.m. to noon, the Folha MS reported.
Why the bridge must be cleared
Concrete placement requires the roadway to be completely free of vehicles. Agesul says traffic during concrete pouring and curing causes vibrations that can compromise the strength of the structure.
Cars and trucks would also pass over workers and equipment on the structure. For that reason, the bridge is closed only during short work windows.
The state chose late afternoon and overnight hours, when traffic is lighter. Even so, the closure lasts through the night and ends only late Thursday morning.

Ambulances can cross; everyone else must wait
Ambulances and public safety vehicles will be allowed through in emergencies, accompanied by Agesul support teams, the state government said in its notice.
The notice gives no alternate route for other traffic. The official guidance is for drivers, freight companies and residents to plan trips in advance and follow signs along the affected section.
In practice, anyone who needs to cross the river has two options: go before 5 p.m. Wednesday or after noon Thursday. Those who arrive during the closure will have to wait at the bridge approach.
For residents, the calculation is simple: a medical appointment, delivery or trip scheduled for Thursday morning will have to move to another day or time.
What has changed since September
In September, I reported here at CPG that about 600 tractor-trailers crossed the bridge each day under 24-hour alternating one-way traffic, with the project scheduled for completion by the end of the first quarter of 2027.
Two months later, the state government reports that 75% of the work is complete. The budget remains unchanged at more than R$11.7 million in state funding.
What has not changed is the single-lane setup. Since June, traffic has moved in one lane under alternating one-way control, supported by temporary steel platforms installed over the structure.
Saturday’s notice gives no completion date and does not name the contractor. The work is being carried out by Agesul in technical cooperation with DNIT, the federal highway authority that owns the road.
A 1,890-meter bridge serving two cities
The bridge is 1,890 meters long and is one of the main access routes to Corumbá and the Pantanal. It carries freight, tourists, and people who live and work in the region.
It is also part of the international freight route to Bolivia, which borders Corumbá, according to the Estradas website.
That means 19 hours of closure affect more than people heading to the Pantanal to sightsee or fish. They also affect trucks carrying fuel, food, and construction materials to supply both cities.
The bridge was tolled for more than a decade
The structure was operated by a concessionaire, Porto Morrinho, which charged a toll to cross. In September 2022, cars paid R$ 14.10, motorcycles R$ 8.50, and nine-axle trucks R$ 126.90, according to Estradas.
The bridge returned to public control in May 2023. The website said it was handed back in less than fully usable condition, after more than 13 years of toll collection.
The state government is footing the bill for rehabilitation, which is expected to cost more than R$ 11.7 million. The work is being carried out by Agesul.
What the government says
Mato Grosso do Sul Infrastructure and Logistics Secretary Guilherme Alcântara de Carvalho says the project is “in the home stretch” and is on schedule.
“Each completed stage brings us closer to the moment when the bridge will be fully rehabilitated,” he said in a statement published by the MS Government News Agency.
The phrase “home stretch” comes with four more closures still to come. The government has not said whether they will follow the pattern of the past two weeks, with a closure every Wednesday.
How to plan for Wednesday and Thursday
Anyone traveling from Corumbá or Ladário to Campo Grande should cross the bridge by 5 p.m. Wednesday (25), local time. After that, the next crossing will be at noon Thursday (26).
The same applies to drivers going in the opposite direction. Anyone leaving Campo Grande needs to allow enough time to reach the bridge before it closes, not after.
Trucking companies with deliveries scheduled in Corumbá for Thursday morning should reschedule or move up their trips. Freight arriving Wednesday night will not enter the city until Thursday afternoon.
Alternating one-way traffic will continue after reopening
When the bridge reopens at noon Thursday (26), traffic will resume on a single lane, with the same signage and alternating traffic control by direction. Alternating one-way traffic will remain in place until rehabilitation is complete; the notice gave no end date.
That means the line of vehicles will not disappear when the closure ends. In the first hours after reopening, vehicles held up on both sides will add to normal afternoon traffic.
Because traffic can move in only one direction at a time, it may take several hours for the approaches to clear. If the trip allows, avoid crossing right at noon.