  3. / To Build Beijing Daxing International Airport, China Poured About 1.6 Million Cubic Meters of Concrete at a Site That Operated as a Continuous Industrial Line for Foundations, Slabs, and Structures of the World’s Largest Single Terminal
Reading time 4 min of reading Comments 0 comments

To Build Beijing Daxing International Airport, China Poured About 1.6 Million Cubic Meters of Concrete at a Site That Operated as a Continuous Industrial Line for Foundations, Slabs, and Structures of the World’s Largest Single Terminal

Written by Valdemar Medeiros
Published on 04/02/2026 at 11:31
Updated on 04/02/2026 at 11:33
Para erguer o Aeroporto Internacional de Pequim-Daxing, a China despejou cerca de 1,6 milhão de m³ de concreto em um canteiro que operou como linha industrial contínua para fundações, lajes e estruturas do maior terminal único do mundo
Para erguer o Aeroporto Internacional de Pequim-Daxing, a China despejou cerca de 1,6 milhão de m³ de concreto em um canteiro que operou como linha industrial contínua para fundações, lajes e estruturas do maior terminal único do mundo
  • Reação
Uma pessoa reagiu a isso.
Reagir ao artigo

The Beijing-Daxing International Airport Used About 1.6 Million m³ of Concrete in a Continuous Industrial Site, with Foundations and Slabs Executed Simultaneously on an Unprecedented Scale.

According to international technical reports, engineering analyses published by major outlets, and the architectural documentation of the project, the Beijing-Daxing International Airport was conceived from the outset as a mass construction project, where the main challenge was not just to erect a gigantic building, but to control concrete volumes on the scale of a small dam, within a rigid schedule imposed by the Chinese state.

Inaugurated in 2019, the airport was born with a clear strategic objective: to alleviate the saturation of the old capital airport and create a new aviation hub capable of handling tens of millions of passengers per year. To achieve this, an architectural concept of a continuous single terminal was adopted, with a built area close to 1 million square meters, which automatically required a structural solution beyond the conventional standard.

A Construction Site Treated as a Concrete Factory

The most impressive data of the project is the total volume of concrete used, estimated at around 1.6 million cubic meters throughout the construction. In engineering terms, this equates to producing, transporting, pouring, and curing concrete without significant interruptions for several months, something impossible on traditional job sites.

YouTube Video

To handle this volume, the construction site was structured as a temporary industrial plant, with:

  • dedicated concrete plants installed on site,
  • permanent internal logistics for aggregates, cement, and additives,
  • and pouring schedules planned to avoid cold joints in large continuous slabs.

In practice, the airport was “printed” on the ground in successive layers of concrete.

Foundations and Slabs Executed Simultaneously

Unlike the classic sequential method, where foundations are completed before starting superstructures, Daxing adopted a strategy of parallel execution.

Large areas of deep foundations, blocks, and piles advanced simultaneously while floor slabs and structural platforms were already being poured in adjacent sectors.

This approach drastically reduced the total construction time but required:

  • strict control of concrete curing,
  • continuous monitoring of deformations and settlements,
  • and extreme coordination between foundation, structural, and installation teams.

An error in a single section could compromise thousands of square meters already executed.

Concrete Pumped on an Unprecedented Scale

YouTube Video

Another critical technical aspect was the pumping of concrete over long horizontal and vertical distances. The radial shape of the terminal required that the material be distributed to structural arms extending hundreds of meters from the central core.

To achieve this, high-capacity pumping systems operated continuously, ensuring:

  • sufficient flow to maintain industrial pace,
  • homogeneity of concrete throughout the route,
  • and rheological stability even in long transport cycles.

This type of operation is common in skyscrapers but rare in horizontal buildings of this extent.

A Single Terminal Supported by a Monolithic Base

The option for a single terminal — instead of several separate buildings — concentrated structural loads in a continuous area. This led to the creation of a monolithic concrete base, where foundations, blocks, and slabs function almost as a single structural body.

From an engineering perspective, this solution improves:

  • the distribution of loads,
  • the control of differential settlements,
  • and long-term structural durability.

On the other hand, it requires concrete volumes far exceeding those of traditional modular airports.

Political Schedule Transformed into Technical Challenge

The Daxing construction was executed under a strict political deadline, with an inauguration date set years in advance. This eliminated margins for weather delays, logistical failures, or project revisions during execution.

YouTube Video

The result was a site that operated 24 hours a day, with continuous shifts, meticulous pouring planning, and real-time technical decisions made to maintain the production flow.

When a Building Becomes Heavy Infrastructure

Although classified as a building, the Beijing-Daxing International Airport behaves, from a construction perspective, like a heavy infrastructure project. The volume of concrete used is not typical of common civil architecture but rather of:

  • large plants,
  • industrial platforms,
  • or medium-sized dams.

This scale explains why the project is frequently cited in studies about the industrialization of construction in China.

YouTube Video

The Daxing has not only become a landmark due to its futuristic design or operational efficiency but has also demonstrated that it is possible to treat gigantic buildings as continuous industrial processes, where concrete, steel, and logistics are managed with the same logic as a production line.

Pouring about 1.6 million m³ of concrete was not a side effect of the project — it was the very construction method chosen to make viable, in just a few years, one of the largest airport terminals ever built on the planet.

Inscreva-se
Notificar de
guest
0 Comentários
Mais recente
Mais antigos Mais votado
Feedbacks
Visualizar todos comentários
Valdemar Medeiros

Formado em Jornalismo e Marketing, é autor de mais de 20 mil artigos que já alcançaram milhões de leitores no Brasil e no exterior. Já escreveu para marcas e veículos como 99, Natura, O Boticário, CPG – Click Petróleo e Gás, Agência Raccon e outros. Especialista em Indústria Automotiva, Tecnologia, Carreiras (empregabilidade e cursos), Economia e outros temas. Contato e sugestões de pauta: valdemarmedeiros4@gmail.com. Não aceitamos currículos!

Share in apps
0
Adoraríamos sua opnião sobre esse assunto, comente!x