1. Home
  2. / Oil and Gas
  3. / Búzios 11 Reaches New Level With Delivery of First Subsea Tree from OneSubsea to Petrobras
Reading time 3 min of reading Comments 3 comments

Búzios 11 Reaches New Level With Delivery of First Subsea Tree from OneSubsea to Petrobras

Written by Corporativo
Published on 28/08/2025 at 17:52
Funcionários da Petrobras e OneSubsea comemoram entrega da primeira árvore de natal molhada para o projeto Búzios 11
Equipe técnica da Petrobras e OneSubsea celebra marco industrial com entrega do primeiro sistema submarino do campo Búzios 11
  • Reaction
  • Reaction
  • Reaction
  • Reaction
  • Reaction
40 people reacted to this.
React to this article

First Delivery Marks New Advance in Pre-Salt

OneSubsea completed, in August 2025, the delivery of the first wet Christmas tree (WCT) intended for Petrobras’s Búzios 11 project.

The factory located in Taubaté (SP) produced the equipment and delivered it within the contractual deadline. This reinforces the established partnership between the two companies.

Contract Provides for 15 Units and Associated Services

The contract signed in 2023 between Petrobras and OneSubsea provides for the supply of 15 wet Christmas trees, as well as electro-hydraulic units.

Also included are installation, commissioning, and maintenance services, essential to ensuring the continuity of operations in the pre-salt.

Since the Búzios 6 project, OneSubsea has secured all the contracts for subsea trees from the state-owned company, consolidating its presence in this strategic segment.

Delivery Reinforces Value of Industrial Partnership

According to Volmir Korzeniewski, Head of Subsea Production System (SPS) Brazil at OneSubsea, the first delivery represents a joint effort and a historic milestone.

During the ceremony in Taubaté, with the presence of Petrobras, it was emphasized that the operator’s recognition confirms the relevance of cooperation and technological advancement.

The partnership, which has lasted for years, has kept the pre-salt schedules within the established deadlines.

Installation Scheduled for 2026

The installation of the first WCT for Búzios 11 is scheduled for the first quarter of 2026 at well BUZ-11.P12, an oil producer.

This equipment will be crucial to allow the new platform to reach its nominal production capacity of 225,000 barrels of oil per day.

It is estimated that each well in the region has an average production of 40,000 barrels of oil per day, reinforcing the importance of this delivery for the pre-salt.

Production Will Be Centralized in Brazilian Units

The OneSubsea industrial unit, located in Taubaté (SP), will be responsible for manufacturing all the wet Christmas trees for the project.
Additionally, the Macaé (RJ) branch will carry out complementary services. These include commissioning and maintenance of the equipment.
Meanwhile, the strategic location of Macaé strengthens its importance in offshore operations. For this reason, the municipality has become a key point in the logistics of the energy industry.

This division of tasks ensures operational efficiency and strengthens regional logistics. While one base manufactures the equipment, the other executes essential services. Thus, the company integrates its structures, reinforcing the synergy between industrial units in different states.

At the same time, the strategy allows for reduced timelines and optimized resources. Although they are distinct operations, the units carefully coordinate the flow between them. This maintains quality, as well as agility in deliveries.

Additionally, this joint action contributes to the maintenance of the national supply chain. While each base has specific functions, both operate in synergy. This supports OneSubsea’s commitment to the Brazilian offshore market.

Therefore, the project demonstrates how territorial integration drives results. Even with logistical challenges, the company ensures consistent performance and adds value to its operations in the country.

Sign up
Notify of
guest
3 Comments
most recent
older Most voted
Built-in feedback
View all comments
Denilson Domingos
Denilson Domingos
30/08/2025 09:44

Tudo isso pra ser entregue pra **** capitalistas liberais! Não há distribuição da riqueza não serve de nada pro país!!

Vânia albino Pimentel
Vânia albino Pimentel
29/08/2025 13:14

Preciso de uma vaga para caldeireiro como faço

Leandro Borges
Leandro Borges
29/08/2025 03:26

Parabéns a todo time da OneSubsea envolvido nesse projeto!!

Last edition 8 months ago for Leandro Borges
Corporativo

CPG Corporate Reports is dedicated to news about events, projects, and announcements from companies in Brazil and globally!

Share in apps
3
0
I'd love to hear your opinion, please comment.x