With Delivery Scheduled for 2026, Line 6-Orange Has Already Excavated 14 Km of Tunnels and Will Integrate with Four Other Lines of the Public Transportation System in São Paulo.
The Line 6-Orange of the SP Metro is progressing rapidly in 2025. The megaproject for urban mobility, which connects Brasilândia in the North Zone to the city center, has already surpassed 60% physical completion. With 15 stations distributed over 15.3 km, the line will have the capacity to transport 630,000 passengers per day.
With a total investment of R$ 19 billion, the works of the São Paulo Metro 2025 are the responsibility of the concessionaire Linha Uni, part of the Spanish group Acciona. The current inauguration deadline is October 2026.
Tunnel Boring Machine Tatuzão Line 6 Accelerates Excavations
Two giant mechanical shields, known as Tunnel Boring Machine Tatuzão Line 6, are the protagonists in the opening of the underground tunnels. By April 2025, more than 14 km have been excavated, including sections between the Água Branca, Perdizes, and Santa Marina stations.
-
Building a 95-square-meter house in 2026 can start at around R$ 185,000 at the reference base and exceed R$ 330,000 in high standard, but the final cost depends on the land, finishing, fees, and the region, with the South of the country being among the most expensive in Brazil.
-
A small church built in 7 weeks in 1961 stands surrounded by skyscrapers in Balneário Camboriú, the city with the most expensive square meter in Brazil, accommodating only 60 people and defying decades of verticalization and luxury on the coast of Santa Catarina.
-
Satellite images analyzed by Reuters reveal that China is building a vast network of over 80 launch platforms, bunkers, and communication centers in the Xinjiang desert near its nuclear silos, in an effort that analysts say aims to ensure the capability to retaliate in the event of an attack.
-
The Supreme Court approved Ferrogrão by nine votes to one, the railway that had been stalled for five years and is expected to provide a shorter route for soybeans from Mato Grosso to flow towards the north of the country.
The Santa Marina Station has already reached 75% of work completed. Stations like 14 Bis–Saracura, which faced archaeological setbacks, have had work resumed with the approval of Iphan.
Next-Generation Trains Arrive in the Second Semester

The 22 trains that will operate on the Line 6-Orange of the SP Metro are being manufactured by Alstom in Taubaté (SP) and will have the capacity to carry up to 2,044 passengers each. Delivery is scheduled for the second semester of 2025.
The line will also feature significant integrations with other metro-rail networks, including lines 1-Blue, 4-Yellow, and CPTM Lines 7 and 8, becoming a key piece in São Paulo’s public transportation.
Expansion Study to Mooca Is Underway
The Government of the State of São Paulo has authorized a feasibility study to expand Line 6-Orange to Mooca, including the neighborhoods of Aclimação and Cambuci. The proposal includes the addition of six new stations, further increasing the coverage of the metro system.
More than 10,500 workers, both direct and indirect, are currently mobilized on the construction sites, which continue to be one of the largest urban infrastructure projects underway in Brazil.

-