  3. / Bridge of Nearly R$ 400 Million in Brazil That Will Connect Cities and Generate Thousands of Jobs Reaches 27% Completion, and Its Construction Can Be Monitored in Real Time
Location PR Reading time 4 min of reading Comments 14 comments

Bridge of Nearly R$ 400 Million in Brazil That Will Connect Cities and Generate Thousands of Jobs Reaches 27% Completion, and Its Construction Can Be Monitored in Real Time

Written by Alisson Ficher
Published on 07/11/2024 at 01:32
Ponte de Guaratuba, no Paraná, avança 27% e promete transformar o litoral com R$ 400 milhões em investimentos. Descubra os detalhes!
Ponte de Guaratuba, no Paraná, avança 27% e promete transformar o litoral com R$ 400 milhões em investimentos. Descubra os detalhes! (Foto: ilustração/ IA)
Seja o primeiro a reagir!
Reagir ao artigo

The expectation is huge, but did you know that one of the largest works in Paraná is about to change the reality of the region? Located on the State Coast, the Guaratuba Bridge is one of the most anticipated projects by the people of Paraná.

With an investment of nearly R$ 400 million, this project promises not only to revolutionize local infrastructure but also to generate thousands of jobs and boost the region’s economy.

And the best part: progress can be tracked in real-time. Want to know more? Keep reading.

The Progress of the Work: 27% Completed with Projected Completion in 2026

The construction of the Guaratuba Bridge is going full steam ahead. According to the October 2024 report published this Wednesday (06), the project has reached the mark of 27.1% completion, which represents more than a quarter of the work completed.

In six months of intense work, the project has followed the schedule rigorously.

The focus has been on infrastructure, highlighting the piles of the stayed and pre-cast sections, and the manufacturing of the longitudinal beams that will support the bridge.

Guaratuba Bridge works complete six months and reach 27.1% execution. (Image: DER)

Execution Details: How the Bridge is Being Built

So far, 24 piles have been completed, with 14 on the stayed section and 10 on the pre-cast section.

In total, the project foresees the construction of 64 piles, with 40 piles in the pre-cast section and 24 in the stayed section.

Additionally, 37 longitudinal beams have already been manufactured, aiming to reach a total of 160 by the end of the work.

The transverse beams have also begun to be assembled, with four already completed and 22 planned to compose the complete structure of the bridge.

The engineer from the Department of Highways of Paraná (DER/PR), Larissa Vieira, stated that the progress of the work is within what was planned.

“The progress has been visible, with quality, safety, and efficiency. Our goal is to deliver a work that will become a landmark for the Paraná coast”, highlighted the engineer.

Economic and Employment Impact in Paraná

The Guaratuba Bridge project has already generated a significant impact on the local economy.

So far, more than 415 workers are directly involved in the construction, and by the end of 2024, this number is expected to reach 600 people.

The expectation is that the completion of the bridge, projected for April 2026, will bring significant benefits for tourism and the economy of the Paraná coast.

Moreover, the project is being executed by a multidisciplinary team composed of engineers, biologists, sailors, oceanographers, masons, welders, among other professionals, who work tirelessly to ensure that the project becomes a reality.

Million-Dollar Investments and Real-Time Monitoring

The Government of Paraná, through DER/PR, is investing R$ 386.9 million in the construction of the Guaratuba Bridge.

To ensure transparency and monitoring of the work, activities can be tracked in real time, through monitoring cameras available on the official project website (https://www.pontedeguaratuba.pr.gov.br/).

According to the latest figures, the investment in October was R$ 104,699,377.72.

The Bridge will be 1,244 meters long, with four traffic lanes, two safety lanes, sidewalks with a bike lane, and a protection system with rigid concrete barriers and guardrails at the ends.

A Project Expected for Decades: The Timeline of the Guaratuba Bridge

The construction of the bridge officially started on April 30, 2024, with the issuance of the Installation License by the Department of Infrastructure and Logistics of the State.

Over the months, several milestones have already been achieved, such as the 1st concreting of piles in the pre-cast section (May), the installation of the crane at the construction site (July), and the 1st transverse beam completed (September).

Check out some important milestones of the work:

  • April: Announcement of the issuance of the Installation License
  • May: 1st concreting of a pile in the pre-cast section
  • June: 1st concreting of a pile in the stayed section
  • July: Installation of the crane at the construction site
  • August: Manufacturing of the 1st longitudinal beam
  • September: Completion of the 1st transverse beam
  • October: Completion of the piles of Support 4 (stayed section)

Expected Delivery and Online Monitoring

The expectation is that the work will be completed by April 2026, with the promise of transforming the mobility and economy of the entire region.

The good news is that, while the work advances, everyone can track the progress via real-time monitoring cameras. Visit the Guaratuba Bridge website and see how the work is being carried out!

With the completion of this mega-project, the Coast of Paraná will see a significant change in its infrastructure and economy. Do you think this bridge will be the key to the region’s growth? Leave your opinion in the comments!

Inscreva-se
Notificar de
guest
14 Comentários
Mais recente
Mais antigos Mais votado
Feedbacks
Visualizar todos comentários
Antonio adorildo dos Santos
Antonio adorildo dos Santos
09/11/2024 22:36

Olá sou pedreiro do Amazonas tem vagas nesta ponte, já trabalhei em ponte no Amazonas QUAL A EMPRESA QUE ESTÁ FASENDO A OBRA NO PARANÁ

Cliceu Macedo
Cliceu Macedo
09/11/2024 13:06

Ratinho o melhor governador que o Paraná já teve merece ser o futuro Presidente da República

Antônio Renan vargas trombini
Antônio Renan vargas trombini
09/11/2024 06:49

Que maravilha uma ótima notícia saber que está gerando empregos contribuindo na evolução e praticidade rapidez no transporte dos interesses dos estados parabéns ao Brasil.

Alisson Ficher

Jornalista formado desde 2017 e atuante na área desde 2015, com seis anos de experiência em revista impressa, passagens por canais de TV aberta e mais de 12 mil publicações online. Especialista em política, empregos, economia, cursos, entre outros temas e também editor do portal CPG. Registro profissional: 0087134/SP. Se você tiver alguma dúvida, quiser reportar um erro ou sugerir uma pauta sobre os temas tratados no site, entre em contato pelo e-mail: alisson.hficher@outlook.com. Não aceitamos currículos!