Eletronuclear Has Already Presented An Acceleration Plan for the Critical Path Works of Angra 3 Nuclear Plant, Where One of the Priorities Is to Complete the Called Containment Building of the Plant
Good news regarding the construction works of the Angra 3 nuclear plant. To ensure that the plant begins operations on schedule – in November 2026, Eletronuclear launches a tender to hire compliance services, aiming to implement and execute a specific corporate integrity program for the critical path works of the plant. Eletronuclear Receives Advance of 2.5 Billion Reais to Resume Works on the Angra 3 Nuclear Plant in 2020
Read Also
- Itapu FPSO Tender Is Canceled; Petrobras Closes Deal with Shell and Petrogal for the Purchase of FPSO P-71 for 353 Million Dollars
- Contractor Providing Services for Petrobras Works at Comperj Files for Bankruptcy, Leaving 200 Workers at a Loss
- 150 Vacancies at Mercedes Benz! The German Multinational Manufacturing Luxury Cars and Trucks Calls for Unexperienced Professionals
The tender opened by the state company is for Specialized Compliance Services to support the Integrity area of ELETROBRAS ELETRONUCLEAR, encompassing risk assessment and auditing, aiming to implement and execute a Specific Corporate Integrity Program (Compliance), dedicated to the Critical Path services of the Angra 3 project.
The notice was published yesterday (10/27) and the submission of proposals has already begun. According to the publication, the proposal opening is scheduled for 2 PM on November 19.
-
Corn outside the window may dry out in May and June: rain will only last until the end of April, El Niño is still uncertain, and three waves of polar air may bring strong frosts as early as the second half of May.
-
China suspends meat imports from a slaughterhouse in Várzea Grande, and the market tries to panic: an analyst says that the ban is common, may affect only one batch, and does not lower cattle prices.
-
With 93 companies selling armored vehicles, aircraft, and monitoring systems to 148 countries, Brazil’s defense industry is doubling exports and is on track to break all records in 2026.
-
Whoever earns R$ 7,000 in Brazil did not receive an exemption from income tax in 2026 and has become the preferred target of the financial system, living in the most dangerous trap of the middle class.
It is worth noting that the state company has already presented an acceleration plan for the so-called critical path works of Angra 3, where one of the priorities is to complete the called containment building of the plant – the most complex building with the highest volume of work in the project until 2023. The start of operations of the Angra 3 nuclear plant is expected for 2026.
ELECTRONIC TENDER NO. DAN.A / PE-224/2020
- Eletrobrás Termonuclear S/A – ELETRONUCLEAR publicly announces that it will conduct a Tender in the form of an Electronic Auction, lowest price, for the Provision of Specialized Compliance Services to support the Integrity area of ELETROBRAS ELETRONUCLEAR, encompassing risk assessment and auditing, aiming to implement and execute a Specific Corporate Integrity Program (Compliance), dedicated to the Critical Path services of the Angra 3 project.
- The Notice can be obtained free of charge through the website www.comprasgovernamentais.gov.br, starting on 10/27/2020.
- The submission of Proposals: starting from 10/27/2020 on the website www.comprasgovernamentais.gov.br.
- Proposal Opening: at 14:00 (two PM) on 11/19/2020, www.comprasgovernamentais.gov.br
Publication Date: 10/27/2020

Seja o primeiro a reagir!