The Duplication of BR-153 Between Goiás and Tocantins, One of the Main Logistics Corridors in the Country, Is Starting to Become a Reality. The Project, Long Awaited, Was Officialized with the Signing of the Service Order in Rialma (GO). In Addition to Representing Billion-Dollar Investments, the Work Promises to Transform Transport, Generate Jobs, and Provide More Safety to Drivers Who Use the Stretch Daily.
The duplication of BR-153/GO/TO officially began this Thursday (21) in Rialma (GO). During the ceremony, federal, state, and municipal authorities emphasized the importance of the project.
The director-general of the National Land Transport Agency (ANTT), Guilherme Theo Sampaio, stated that the undertaking will bring improvements in road safety, regional development, and infrastructure modernization.
Extension and Investments
The plan provides for 60.48 km of duplicated highway, in addition to 27.22 km of service roads, 14 turnarounds, 8 devices, 3 pedestrian bridges, and 2 accesses.
-
656 apartments and units starting from R$ 234 thousand will build a new vertical neighborhood in Blumenau, transform Velha Grande in three years, and expand the Minha Casa, Minha Vida program’s investment in the city’s expansion.
-
WEG created a battery storage system that is transforming an old mine in Finland into a renewable energy hub. The project is one of the first hybrids in the Nordic country to combine solar generation with storage and helps stabilize the national electricity grid.
-
The most expensive stadium on the planet cost R$ 30 billion to be built in Los Angeles and will host eight games of the 2026 World Cup. The 110-meter screen is larger than the playing field itself, and the roof projects videos that airplane passengers see during landing at the airport.
-
The vertical neighborhood with 656 apartments starting from R$ 234,000, which is being built in Blumenau, is expected to be ready in three years. MRV’s mega-condominium occupies a 70,000-square-meter plot in Velha Grande and qualifies for band 2 of Minha Casa Minha Vida.
Municipalities such as Figueirópolis, Alvorada, Talismã, Campinorte, Uruaçu, Rialma, and Rianápolis will be included.
The investment exceeds R$ 500 million, financed by the Amazon Bank (BASA) and BNDES.
The project is expected to generate about 1,400 direct jobs and 2,400 indirect jobs.
Deadlines and Expectations
According to the schedule, the completion of the works is expected in October 2026, with operations starting on September 30 of the same year.
The duplication is expected to directly benefit the 23,000vehicles that circulate daily through the stretch, increasing traffic capacity and ensuring more comfort for users.
Relevance to the Country
During the event, Guilherme Theo Sampaio highlighted the project’s impact.
“We are by the BR-153 giving the service order for the first 60 km of duplication. There is more than R$ 600 million in investment, and we won’t stop there. By the end of the ten-year concession, we will have the entire BR-153 duplicated in the state of Goiás. What does this mean? More road safety, efficiency in transportation, job and income generation, and ANTT being part of this national transformation,” he stated.
In addition to reducing accidents, the duplication will facilitate the flow of agricultural production and strengthen the region’s logistical competitiveness. ANTT will monitor every step of the work to ensure deadlines and quality, benefiting the population.