In 2025, the Secretary of Agriculture of Alegrete coordinated the drilling of six community artesian wells in Jararaca, Durasnal, Rincão do 28, Pinheiros, Jacaquá, and Encruzilhada, with amendments from Cléo Trindade, Éder Fioravante, Firmina Soares, and Fátima Marchezan. The one in Pinheiros, completed on the 29th, serves five families in the rural area.
In 2025, Alegrete advanced water supply in the countryside with the drilling of 06 artesian wells in six locations, coordinated by the Secretary of Agriculture. On the last day of the month, the well in the Pinheiros location was completed, with an expectation of serving at least 05 families.
The Secretary informs that, next week, the contracted company will resume activities to deliver the well in the Jacaquá location. This initiative is part of the work developed by the department, focusing on expanding access to water in rural communities.
Where the Artesian Wells Were Drilled in 2025
According to the presented data, in 2025, 06 community artesian wells were drilled in the following locations:
-
The construction company that built Itaipu, Brasília, and Line 4 of the Rio Metro, Andrade Gutierrez, files its second out-of-court reorganization in four and a half years in Belo Horizonte with R$ 3.4 billion in debts and 47% of the projects halted.
-
Austrian engineers have developed an inflatable concrete technology that transforms flat slabs into domes using only air pressure, eliminating scaffolding and temporary forms, and potentially changing the way bridges, tunnels, and curved roofs are constructed worldwide.
-
Living cement that repairs cracks and fissures on its own is now being used by construction companies after research proved that dormant bacteria automatically produce limestone, reducing infiltrations, steel corrosion, and million-dollar maintenance costs in bridges and buildings.
-
For the first time in the Americas, a subway will be built and operated from start to finish by Chinese companies, and this is happening in Bogotá, where Line 1 has already surpassed 75% of the construction, with driverless electric trains manufactured in Qingdao arriving by ship.
- Jararaca
- Durasnal
- Rincão do 28
- Pinheiros
- Jacaquá
- Encruzilhada
The coordination of the work was with the Secretary of Agriculture of Alegrete, as part of the actions conducted by the department to expand supply in the countryside.
How the Municipality Funded the Artesian Wells
To make the drilling of the artesian wells feasible, resources from mandatory amendments from the councilors were used:
- Cléo Trindade
- Éder Fioravante
- Firmina Soares
and also from former councilor Fátima Marchezan.
The execution is carried out by a contracted company, with the supervision and coordination of the Secretary.
Well in Pinheiros: Completed on the 29th and Minimum Service Informed
The well in the Pinheiros location was completed on the 29th.
The official information is that it will serve at least 05 families, reinforcing water supply in the countryside and directly serving rural residents.
Next Delivery: Well in Jacaquá with Resumption Next Week
The Secretary states that, next week, the company will resume activities to deliver the well in the Jacaquá location.
The continuity forecast indicates that the artesian wells continue to be a practical axis of the supply strategy in the countryside.
Next Step: Partnership with Incra to Bring Water Network to Settlements
For next year, the Secretary intends to address a long-standing demand within agrarian reform settlements, seeking to meet the needs of these rural communities.
The planned design is:
- The city hall provides resources for the drilling of artesian wells
- Incra transfers to the water distribution network to the houses, including hoses, water tank, tower, pumping station, among other items