NOV Flexibles Signed Contract With Petrobras To Supply 137 Km Of Flexible Pipes
Surpassing two competitors in a bidding process promoted by Petrobras, NOV Flexibles signed a contract with the state-owned company to supply 137 km of flexible pipes. The scope also includes the loading service for pipes and rental of reels.
- Giant In Civil Construction, Andrade Gutierrez Opens 15 Job Vacancies For São Paulo And Belo Horizonte
- Petrobras Announces Sale Of All Assets In Petrobras Colombia
- Less Than 10 Million m³ Per Day Of Natural Gas! YPFB Reduces Delivery To Petrobras
To secure the contract, NOV faced TechnipFMC and GE O&G. The contract value has not yet been disclosed, but it is known that NOV’s bid in the auction was R$ 633.577 million. The bid from Flexibrás (TechnipFMC) was R$ 975 million and from GE O&G was R$ 1.123 billion.
-
Oil at the center of global disputes and historical transformations
-
More than R$ 526 million generated in oil in 2025 was not enough to place Espírito Santo in the lead of innovation — and the data shows exactly where the bottleneck is.
-
With salaries of up to R$ 30,000 and 2,500 open positions, a shipyard in Aracruz (ES) is at the center of a billion-dollar project by Petrobras that involves platforms capable of producing 225,000 barrels per day.
-
Impacts of tensions in the Middle East: how the rise in oil prices is transforming infrastructure contracts in Brazil, raising prices, delaying schedules, and exposing billion-dollar fragility in the sector.
Technip filed appeals arguing that NOV’s proposal would be unfeasible, which was rejected by Petrobras.
The contract will last for four years and the pipes contracted by the company will be of 6” diameter production (44.2 km), 8” production (12.9 km), 57.7 km of 4” gas lift, and 22.2 km of 6” water injection.
NOV has a flexible pipe factory at Porto do Açu, in São João da Barra, in the state of Rio de Janeiro, which has been operating since 2012.
The deliveries of the pipes may be made, upon Petrobras’ request, in Niterói (RJ), Vitória (ES), or at the supplier’s factory, if the freight value is not included.