OEC Will Build Reservoir and New Cedae Pipelines, in Addition to Capacity for 55,000 Cubic Meters and Nearly Five Kilometers of Pipelines
The government of the state of Rio de Janeiro has green-lighted the construction of the New Guandu water production system, the Novo Marapicú reservoir, and five kilometers of pipelines in Nova Iguaçu, in the municipality of Baixada Fluminense. Cedae has made an investment in the necessary infrastructure (Companhia de Águas e Esgotos do Estado do Rio de Janeiro). OEC – Engineering and Construction will be responsible for the construction of the facility, which will have a storage capacity of 55,000 cubic meters.
More than three million people in the cities of Nova Iguaçu, Duque de Caxias, São João de Meriti, Nilópolis, and Belford Roxo, in addition to the capital of the state of Rio de Janeiro, will benefit from the system aimed at increasing the supply of treated water to Baixada Fluminense, ensuring operational security and agility to the Guandu system.
Specificities of the System to be Executed by OEC
The treated water pipeline, with a length of 3,900 meters and a diameter of 2.5 meters, will transport water pumped from the New Guandu ETA to the reservoir. The distribution trunk will have a diameter of 2.5 meters and a total length of about one thousand meters. It will connect the reservoir to the main pipeline of Baixada Fluminense. The total length of the spillway is 940 meters, and its width is 1.5 meters; it directs water from the reservoir to the canal on Ingá Street.
-
Material practically banned for almost 90 years makes a strong comeback in construction: made of hemp and lime, it insulates 15 times more than concrete, absorbs CO₂ over the centuries, and challenges an industry that helped push it out of the market.
-
Australia prepares to dredge 96.5 million m³ in Moreton Bay to deepen, widen, and realign channels of the Port of Brisbane, in a project of up to 25 years designed to accommodate larger ships and enhance maritime safety and regional port efficiency.
-
The largest duplication viaduct in SC is 80 meters long and is taking shape at the intersection with SC-415, while the 15.5-kilometer stretch on the axis between Joinville and Blumenau reaches 31.7% completion with two more viaducts and two bridges under simultaneous construction.
-
Largest load ever received by Egypt travels 247 km on Mammoet self-propelled transporters, with a 1,220-ton hydrorefinery reactor, 102 axles, tunnel reinforcement, and a route prepared to cross even the heavy traffic of Cairo.
Carbon steel will be used in the design of all these buildings. Building Information Modeling (BIM) will be used to support the work, and it is a collection of procedures and tools that enable a radical digital transformation from the design phase to the asset management phase.
The project’s duration is 30 months, with a projected budget of R$ 278 million and an expected start in February 2023. The forecast is for 400 workers and about 46 pieces of equipment at peak production.
“All of us here in Rio de Janeiro are excited to have the opportunity to contribute to a project that will have such a positive effect on the city’s residents. We are happy to be part of this important Cedae project that will improve the lives of many people,” highlights OEC’s Contracts Director, Rogério Dourado.
Job Openings
No official information has yet been provided regarding job openings offered by Odebrecht Engineering and Construction specifically for this project, but the company has an official channel for those who wish to submit their resumes to the database by accessing it here. Any updates or alternative application methods will be reflected in this article.
About Odebrecht Engineering and Construction (OEC)
More than 2,900 large projects, including hydroelectric, thermal, and nuclear plants, bridges, viaducts, tunnels, subway and urban train lines, airports, ports, railways, refineries, industrial and mining works, have been completed under OEC’s supervision over the 78 years of the company’s operations.
As one of the most awarded Latin American firms, OEC received the Global Best Projects award from the prestigious U.S. publication ENR – Engineering News-Record. This award is widely regarded as the “Oscar” of the global engineering industry. Since 2014, OEC has held the Gold Seal of the GHG Protocol program, which compiles inventories of greenhouse gas emissions, in recognition of its commitment to sustainability. Currently, OEC employs over 18,000 people from a wide variety of cultural backgrounds in more than twenty projects in countries across the Americas and Africa.